Heavy Truck EBS Electronic Brake Valve

Product family: Dual-Circuit Pneumatic Valves.

Flow: Die-cast aluminum supplier → Multi-Axis Pressure Port CNC → Ball Burnish & Valve Honing → Diaphragm & Coil Insertion → Software ECU Parameter Flash → Pressure Step Decay Bench → Trailer & Truck Chassis

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: Heavy Truck EBS Electronic Brake ValveSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Die-cast aluminum supplier → Multi-Axis Pressure Port CNC (42.0 s) → Ball Burnish & Valve Honing (51.0 s) → Diaphragm & Coil Insertion (64.0 s) → Software ECU Parameter Flash (48.0 s) → Pressure Step Decay Bench (34.8 s) → Trailer & Truck Chassis.SUPPLIERDie-castaluminumsupplierI2.00 d1Multi-AxisPressure Port CNCC/T 42.0 sI2.20 d2Ball Burnish &Valve HoningC/T 51.0 sI2.40 d3Diaphragm & CoilInsertionC/T 64.0 sI1.50 d4Software ECUParameter FlashC/T 48.0 sI0.90 d5Pressure StepDecay BenchC/T 34.8 sI2.00 dCUSTOMERTrailer & TruckChassis900 / units

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Multi-Axis Pressure Port CNC42.0 s35 min94%98.8%9001,800 (2.00 d)1,148
2. Ball Burnish & Valve Honing51.0 s50 min89%96.5%9001,980 (2.20 d)859
3. Diaphragm & Coil Insertion64.0 s40 min84%95.2%4502,160 (2.40 d)615
4. Software ECU Parameter Flash48.0 s30 min91%97.1%9001,350 (1.50 d)961
5. Pressure Step Decay Bench34.8 s10 min96%98.9%225810 (0.90 d)1,408

Key figures

Takt time
60.0 s
Lead time
11.0 d
Value-added time
240 s
Process cycle efficiency (PCE)
0.040%
Rolled throughput yield (RTY)
87.2%
Customer demand per day
900 units
Line capacity per day
615 units
Bottleneck
Diaphragm & Coil Insertion

Reading the bottleneck

The bottleneck is "Diaphragm & Coil Insertion": it can process 615 units per day against a demand of 900 units, so it falls short of demand by 31.7%. Once downtime and scrap are counted, its cycle time grows from 64.0 s to 80.0 s, against a takt of 60.0 s. The largest loss at this step is equipment downtime (uptime 84%), about 12.2 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.