12m Low-Floor Electric Transit Bus Build

Product family: Zero-Emission City Buses.

Flow: Drive & battery Tier-1 supplier → Stainless Spaceframe Jig → Composite Side Skin Bond → Roof LFP Pack & Pantograph → Floor, Seats & Wheelchair Ramp → High-Voltage Track Test → Municipal Transit Authorities

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: 12m Low-Floor Electric Transit Bus BuildSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Drive & battery Tier-1 supplier → Stainless Spaceframe Jig (1,575 s) → Composite Side Skin Bond (1,913 s) → Roof LFP Pack & Pantograph (2,408 s) → Floor, Seats & Wheelchair Ramp (1,800 s) → High-Voltage Track Test (1,305 s) → Municipal Transit Authorities.SUPPLIERDrive & batteryTier-1 supplierI2.00 d1StainlessSpaceframe JigC/T 1,575 sI2.17 d2Composite SideSkin BondC/T 1,913 sI2.42 d3Roof LFP Pack &PantographC/T 2,408 sI1.50 d4Floor, Seats &Wheelchair RampC/T 1,800 sI0.92 d5High-VoltageTrack TestC/T 1,305 sI2.00 dCUSTOMERMunicipalTransit…12 / units

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Stainless Spaceframe Jig1,575 s35 min94%98.8%1224 (2.00 d)15
2. Composite Side Skin Bond1,913 s50 min89%96.5%1226 (2.17 d)11
3. Roof LFP Pack & Pantograph2,408 s40 min84%95.2%629 (2.42 d)7
4. Floor, Seats & Wheelchair Ramp1,800 s30 min91%97.1%1218 (1.50 d)12
5. High-Voltage Track Test1,305 s10 min96%98.9%311 (0.92 d)18

Key figures

Takt time
2,250 s
Lead time
11.3 d
Value-added time
9,001 s
Process cycle efficiency (PCE)
2.9%
Rolled throughput yield (RTY)
87.2%
Customer demand per day
12 units
Line capacity per day
7 units
Bottleneck
Roof LFP Pack & Pantograph

Reading the bottleneck

The bottleneck is "Roof LFP Pack & Pantograph": it can process 7 units per day against a demand of 12 units, so it falls short of demand by 38.6%. Once downtime and scrap are counted, its cycle time grows from 2,408 s to 3,011 s, against a takt of 2,250 s. The largest loss at this step is equipment downtime (uptime 84%), about 459 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.