CVT Continuous Agricultural Tractor Gearbox

Product family: 300HP Stepless Hydrostatic CVT.

Flow: Tractor casting foundry → Heavy Horizontal Case CNC → Axial Hydrostat Pump Fit → Planetary & Wet Clutch Stack → Electro-Hydraulic Valve Calib → 300HP Back-to-Back Dyno → Tractor Skid Line

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: CVT Continuous Agricultural Tractor GearboxSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Tractor casting foundry → Heavy Horizontal Case CNC (582 s) → Axial Hydrostat Pump Fit (706 s) → Planetary & Wet Clutch Stack (889 s) → Electro-Hydraulic Valve Calib (665 s) → 300HP Back-to-Back Dyno (482 s) → Tractor Skid Line.SUPPLIERTractor castingfoundryI2.00 d1Heavy HorizontalCase CNCC/T 582 sI2.20 d2Axial HydrostatPump FitC/T 706 sI2.40 d3Planetary & WetClutch StackC/T 889 sI1.51 d4Electro-HydraulicValve CalibC/T 665 sI0.91 d5300HPBack-to-Back DynoC/T 482 sI2.00 dCUSTOMERTractor SkidLine65 / units

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Heavy Horizontal Case CNC582 s35 min94%98.8%65130 (2.00 d)83
2. Axial Hydrostat Pump Fit706 s50 min89%96.5%65143 (2.20 d)62
3. Planetary & Wet Clutch Stack889 s40 min84%95.2%33156 (2.40 d)44
4. Electro-Hydraulic Valve Calib665 s30 min91%97.1%6598 (1.51 d)69
5. 300HP Back-to-Back Dyno482 s10 min96%98.9%1659 (0.91 d)102

Key figures

Takt time
831 s
Lead time
11.1 d
Value-added time
3,324 s
Process cycle efficiency (PCE)
0.56%
Rolled throughput yield (RTY)
87.2%
Customer demand per day
65 units
Line capacity per day
44 units
Bottleneck
Planetary & Wet Clutch Stack

Reading the bottleneck

The bottleneck is "Planetary & Wet Clutch Stack": it can process 44 units per day against a demand of 65 units, so it falls short of demand by 31.8%. Once downtime and scrap are counted, its cycle time grows from 889 s to 1,112 s, against a takt of 831 s. The largest loss at this step is equipment downtime (uptime 84%), about 169 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.