40ft Curtain-Sider Semi-Trailer Frame

Product family: Galvanized I-Beam Logistics Trailers.

Flow: I-beam steel supplier → Automated Plasma Beam Cut → Twin-Wire SAW Web Welding → Hot-Dip Zinc Galvanize → Air Suspension & EBS Pipe → Curtain Roof & DOT Inspection → Logistics Haulage Fleets

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: 40ft Curtain-Sider Semi-Trailer FrameSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. I-beam steel supplier → Automated Plasma Beam Cut (394 s) → Twin-Wire SAW Web Welding (478 s) → Hot-Dip Zinc Galvanize (602 s) → Air Suspension & EBS Pipe (450 s) → Curtain Roof & DOT Inspection (326 s) → Logistics Haulage Fleets.SUPPLIERI-beam steelsupplierI2.00 d1Automated PlasmaBeam CutC/T 394 sI2.21 d2Twin-Wire SAW WebWeldingC/T 478 sI2.40 d3Hot-Dip ZincGalvanizeC/T 602 sI1.50 d4Air Suspension &EBS PipeC/T 450 sI0.90 d5Curtain Roof &DOT InspectionC/T 326 sI2.00 dCUSTOMERLogisticsHaulage Fleets48 / units

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Automated Plasma Beam Cut394 s35 min94%98.8%4896 (2.00 d)59
2. Twin-Wire SAW Web Welding478 s50 min89%96.5%48106 (2.21 d)43
3. Hot-Dip Zinc Galvanize602 s40 min84%95.2%24115 (2.40 d)29
4. Air Suspension & EBS Pipe450 s30 min91%97.1%4872 (1.50 d)49
5. Curtain Roof & DOT Inspection326 s10 min96%98.9%1243 (0.90 d)72

Key figures

Takt time
563 s
Lead time
11.1 d
Value-added time
2,250 s
Process cycle efficiency (PCE)
0.75%
Rolled throughput yield (RTY)
87.2%
Customer demand per day
48 units
Line capacity per day
29 units
Bottleneck
Hot-Dip Zinc Galvanize

Reading the bottleneck

The bottleneck is "Hot-Dip Zinc Galvanize": it can process 29 units per day against a demand of 48 units, so it falls short of demand by 38.6%. Once downtime and scrap are counted, its cycle time grows from 602 s to 753 s, against a takt of 563 s. The largest loss at this step is equipment downtime (uptime 84%), about 115 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.