Dual-Standard CCS2 / NACS Motorized Inlet
Product family: Liquid-Cooled Charge Inlets.
Flow: Connector & pin supplier → Pin Turning & Silver Plate → PA66 Flame-Retard Mold → Temp Sensor Solder & Pot → Actuator Lock Assembly → 2kV Dielectric & Lock Cycle → OEM Quarter-Panel Line
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. Pin Turning & Silver Plate | 26.6 s | 55 min | 92% | 97.8% | 1,500 | 2,250 (1.50 d) | 1,715 |
| 2. PA66 Flame-Retard Mold | 30.6 s | 30 min | 91% | 96.9% | 900 | 2,100 (1.40 d) | 1,470 |
| 3. Temp Sensor Solder & Pot | 39.6 s | 20 min | 84% | 94.5% | 1,800 | 4,200 (2.80 d) | 1,062 |
| 4. Actuator Lock Assembly | 28.1 s | 18 min | 93% | 98.2% | 450 | 1,500 (1.00 d) | 1,638 |
| 5. 2kV Dielectric & Lock Cycle | 21.6 s | 12 min | 96% | 99.3% | 225 | 1,050 (0.70 d) | 2,171 |
Key figures
- Takt time
- 36.0 s
- Lead time
- 8.60 d
- Value-added time
- 147 s
- Process cycle efficiency (PCE)
- 0.032%
- Rolled throughput yield (RTY)
- 87.3%
- Customer demand per day
- 1,500 units
- Line capacity per day
- 1,062 units
- Bottleneck
- Temp Sensor Solder & Pot
Reading the bottleneck
The bottleneck is "Temp Sensor Solder & Pot": it can process 1,062 units per day against a demand of 1,500 units, so it falls short of demand by 29.2%. Once downtime and scrap are counted, its cycle time grows from 39.6 s to 49.9 s, against a takt of 36.0 s. The largest loss at this step is equipment downtime (uptime 84%), about 7.5 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of EV Batteries & E-Powertrain: EV Batteries & E-Powertrain
- High-Nickel NMC Prismatic Cell Line
- LFP Cell-to-Pack (CTP) Blade Line
- Vacuum-Brazed Aluminum Battery Cold Plate
- Shielded 800V Orange HV Cable Harness
- 22kW Bi-Directional On-Board Charger
- Automotive ASIL-D Battery Management Controller
- 3kW 800V-to-12V DC-DC Step-Down Unit
- High-Voltage Pyrotechnic Safety Fuse
- 48V Belt-Starter & Lithium Sub-Pack
- Solid-State Oxide Electrolyte Pilot Line
- Standardized Battery-Swap Pack Station