3kW 800V-to-12V DC-DC Step-Down Unit

Product family: Isolated EV Auxiliary Converter.

Flow: Ferrite & power-chip supplier → Die-Cast Heat-Sink Mill → Power Stage SMT Paste → Gap-Pad & Case Torque → ESS Thermal Cycle Shock → Efficiency Curve EOL Sweep → BEV Electrical Architecture

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: 3kW 800V-to-12V DC-DC Step-Down UnitSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Ferrite & power-chip supplier → Die-Cast Heat-Sink Mill (42.0 s) → Power Stage SMT Paste (48.0 s) → Gap-Pad & Case Torque (63.0 s) → ESS Thermal Cycle Shock (44.0 s) → Efficiency Curve EOL Sweep (34.1 s) → BEV Electrical Architecture.SUPPLIERFerrite &power-chipsupplierI1.50 d1Die-CastHeat-Sink MillC/T 42.0 sI1.40 d2Power Stage SMTPasteC/T 48.0 sI2.80 d3Gap-Pad & CaseTorqueC/T 63.0 sI1.00 d4ESS Thermal CycleShockC/T 44.0 sI0.70 d5Efficiency CurveEOL SweepC/T 34.1 sI1.20 dCUSTOMERBEV ElectricalArchitecture950 / units

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Die-Cast Heat-Sink Mill42.0 s55 min92%97.8%9501,425 (1.50 d)1,086
2. Power Stage SMT Paste48.0 s30 min91%96.9%5701,330 (1.40 d)937
3. Gap-Pad & Case Torque63.0 s20 min84%94.5%1,1402,660 (2.80 d)668
4. ESS Thermal Cycle Shock44.0 s18 min93%98.2%285950 (1.00 d)1,046
5. Efficiency Curve EOL Sweep34.1 s12 min96%99.3%143665 (0.70 d)1,376

Key figures

Takt time
56.8 s
Lead time
8.60 d
Value-added time
231 s
Process cycle efficiency (PCE)
0.050%
Rolled throughput yield (RTY)
87.3%
Customer demand per day
950 units
Line capacity per day
668 units
Bottleneck
Gap-Pad & Case Torque

Reading the bottleneck

The bottleneck is "Gap-Pad & Case Torque": it can process 668 units per day against a demand of 950 units, so it falls short of demand by 29.7%. Once downtime and scrap are counted, its cycle time grows from 63.0 s to 79.4 s, against a takt of 56.8 s. The largest loss at this step is equipment downtime (uptime 84%), about 12.0 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.