Standardized Battery-Swap Pack Station
Product family: Quick-Lock 75kWh Swap Packs.
Flow: Battery Tier-1 suppliers → Quick-Lock Coupler CNC → Drip-Free Fluid Valve Mate → Laser Module Weld & Frame → Automated Swap Rig Latches → 50-Cycle Quick-Swap Stress → Swap Station Network
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. Quick-Lock Coupler CNC | 250 s | 55 min | 92% | 97.8% | 160 | 240 (1.50 d) | 182 |
| 2. Drip-Free Fluid Valve Mate | 287 s | 30 min | 91% | 96.9% | 96 | 224 (1.40 d) | 157 |
| 3. Laser Module Weld & Frame | 371 s | 20 min | 84% | 94.5% | 192 | 448 (2.80 d) | 113 |
| 4. Automated Swap Rig Latches | 263 s | 18 min | 93% | 98.2% | 48 | 160 (1.00 d) | 175 |
| 5. 50-Cycle Quick-Swap Stress | 203 s | 12 min | 96% | 99.3% | 24 | 112 (0.70 d) | 231 |
Key figures
- Takt time
- 338 s
- Lead time
- 8.63 d
- Value-added time
- 1,374 s
- Process cycle efficiency (PCE)
- 0.29%
- Rolled throughput yield (RTY)
- 87.3%
- Customer demand per day
- 160 packs
- Line capacity per day
- 113 packs
- Bottleneck
- Laser Module Weld & Frame
Reading the bottleneck
The bottleneck is "Laser Module Weld & Frame": it can process 113 packs per day against a demand of 160 packs, so it falls short of demand by 29.1%. Once downtime and scrap are counted, its cycle time grows from 371 s to 467 s, against a takt of 338 s. The largest loss at this step is equipment downtime (uptime 84%), about 70.7 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of EV Batteries & E-Powertrain: EV Batteries & E-Powertrain
- High-Nickel NMC Prismatic Cell Line
- LFP Cell-to-Pack (CTP) Blade Line
- Vacuum-Brazed Aluminum Battery Cold Plate
- Shielded 800V Orange HV Cable Harness
- 22kW Bi-Directional On-Board Charger
- Automotive ASIL-D Battery Management Controller
- 3kW 800V-to-12V DC-DC Step-Down Unit
- Dual-Standard CCS2 / NACS Motorized Inlet
- High-Voltage Pyrotechnic Safety Fuse
- 48V Belt-Starter & Lithium Sub-Pack
- Solid-State Oxide Electrolyte Pilot Line