Shielded 800V Orange HV Cable Harness

Product family: Corrugated EV HV Looms.

Flow: Copper foil & PE supplier → Auto Reel Cut & Foil Strip → Ultrasonic Ring Weld Lug → Shrink Tube & Shield Braid → HV Plug Click & Seal → 3kV Hipot & Pin Continuity → BEV Drivetrain & Charger

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: Shielded 800V Orange HV Cable HarnessSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Copper foil & PE supplier → Auto Reel Cut & Foil Strip (32.0 s) → Ultrasonic Ring Weld Lug (36.7 s) → Shrink Tube & Shield Braid (48.0 s) → HV Plug Click & Seal (33.7 s) → 3kV Hipot & Pin Continuity (25.9 s) → BEV Drivetrain & Charger.SUPPLIERCopper foil &PE supplierI1.50 d1Auto Reel Cut &Foil StripC/T 32.0 sI1.40 d2Ultrasonic RingWeld LugC/T 36.7 sI2.80 d3Shrink Tube &Shield BraidC/T 48.0 sI1.00 d4HV Plug Click &SealC/T 33.7 sI0.70 d53kV Hipot & PinContinuityC/T 25.9 sI1.20 dCUSTOMERBEV Drivetrain& Charger1,250 / units

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Auto Reel Cut & Foil Strip32.0 s55 min92%97.8%1,2501,875 (1.50 d)1,426
2. Ultrasonic Ring Weld Lug36.7 s30 min91%96.9%7501,750 (1.40 d)1,225
3. Shrink Tube & Shield Braid48.0 s20 min84%94.5%1,5003,500 (2.80 d)876
4. HV Plug Click & Seal33.7 s18 min93%98.2%3751,250 (1.00 d)1,366
5. 3kV Hipot & Pin Continuity25.9 s12 min96%99.3%188875 (0.70 d)1,811

Key figures

Takt time
43.2 s
Lead time
8.60 d
Value-added time
176 s
Process cycle efficiency (PCE)
0.038%
Rolled throughput yield (RTY)
87.3%
Customer demand per day
1,250 units
Line capacity per day
876 units
Bottleneck
Shrink Tube & Shield Braid

Reading the bottleneck

The bottleneck is "Shrink Tube & Shield Braid": it can process 876 units per day against a demand of 1,250 units, so it falls short of demand by 29.9%. Once downtime and scrap are counted, its cycle time grows from 48.0 s to 60.5 s, against a takt of 43.2 s. The largest loss at this step is equipment downtime (uptime 84%), about 9.1 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.