22kW Bi-Directional On-Board Charger

Product family: V2G Liquid-Cooled OBC Unit.

Flow: GaN device & passives supplier → Double-Sided SMT Reflow → Planar Transformer Pot → Cold-Plate Thermal Interface → High-Temp 85°C Burn-In → Bidirectional Grid Simulation → EV Front Frunk Assembly

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: 22kW Bi-Directional On-Board ChargerSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. GaN device & passives supplier → Double-Sided SMT Reflow (64.0 s) → Planar Transformer Pot (74.0 s) → Cold-Plate Thermal Interface (96.0 s) → High-Temp 85°C Burn-In (68.0 s) → Bidirectional Grid Simulation (52.0 s) → EV Front Frunk Assembly.SUPPLIERGaN device &passivessupplierI1.50 d1Double-Sided SMTReflowC/T 64.0 sI1.40 d2PlanarTransformer PotC/T 74.0 sI2.80 d3Cold-PlateThermal InterfaceC/T 96.0 sI1.00 d4High-Temp 85°CBurn-InC/T 68.0 sI0.70 d5BidirectionalGrid SimulationC/T 52.0 sI1.20 dCUSTOMEREV Front FrunkAssembly620 / units

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Double-Sided SMT Reflow64.0 s55 min92%97.8%620930 (1.50 d)713
2. Planar Transformer Pot74.0 s30 min91%96.9%372868 (1.40 d)608
3. Cold-Plate Thermal Interface96.0 s20 min84%94.5%7441,736 (2.80 d)438
4. High-Temp 85°C Burn-In68.0 s18 min93%98.2%186620 (1.00 d)677
5. Bidirectional Grid Simulation52.0 s12 min96%99.3%93434 (0.70 d)902

Key figures

Takt time
87.1 s
Lead time
8.61 d
Value-added time
354 s
Process cycle efficiency (PCE)
0.076%
Rolled throughput yield (RTY)
87.3%
Customer demand per day
620 units
Line capacity per day
438 units
Bottleneck
Cold-Plate Thermal Interface

Reading the bottleneck

The bottleneck is "Cold-Plate Thermal Interface": it can process 438 units per day against a demand of 620 units, so it falls short of demand by 29.3%. Once downtime and scrap are counted, its cycle time grows from 96.0 s to 121 s, against a takt of 87.1 s. The largest loss at this step is equipment downtime (uptime 84%), about 18.3 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.