High-Nickel NMC Prismatic Cell Line

Product family: 280Ah Prismatic EV Cells.

Flow: NMC cathode-material supplier → Twin-Shaft Slurry Coat → Vacuum Calender & Slit → Jelly-Roll Wind & Can Weld → Vacuum Electrolyte Fill & Age → ACIR OCV Grading & Sort → EV Module Pack Plants

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: High-Nickel NMC Prismatic Cell LineSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. NMC cathode-material supplier → Twin-Shaft Slurry Coat (16.6 s) → Vacuum Calender & Slit (19.1 s) → Jelly-Roll Wind & Can Weld (24.8 s) → Vacuum Electrolyte Fill & Age (17.6 s) → ACIR OCV Grading & Sort (13.5 s) → EV Module Pack Plants.SUPPLIERNMCcathode-materialsupplierI1.50 d1Twin-Shaft SlurryCoatC/T 16.6 sI1.40 d2Vacuum Calender &SlitC/T 19.1 sI2.80 d3Jelly-Roll Wind &Can WeldC/T 24.8 sI1.00 d4VacuumElectrolyte Fill…C/T 17.6 sI0.70 d5ACIR OCV Grading& SortC/T 13.5 sI1.20 dCUSTOMEREV Module PackPlants3,600 / units

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Twin-Shaft Slurry Coat16.6 s55 min92%97.8%3,6005,400 (1.50 d)4,212
2. Vacuum Calender & Slit19.1 s30 min91%96.9%2,1605,040 (1.40 d)3,601
3. Jelly-Roll Wind & Can Weld24.8 s20 min84%94.5%4,32010,080 (2.80 d)2,561
4. Vacuum Electrolyte Fill & Age17.6 s18 min93%98.2%1,0803,600 (1.00 d)4,016
5. ACIR OCV Grading & Sort13.5 s12 min96%99.3%5402,520 (0.70 d)5,381

Key figures

Takt time
22.5 s
Lead time
8.60 d
Value-added time
91.6 s
Process cycle efficiency (PCE)
0.013%
Rolled throughput yield (RTY)
87.3%
Customer demand per day
3,600 units
Line capacity per day
2,561 units
Bottleneck
Jelly-Roll Wind & Can Weld

Reading the bottleneck

The bottleneck is "Jelly-Roll Wind & Can Weld": it can process 2,561 units per day against a demand of 3,600 units, so it falls short of demand by 28.9%. Once downtime and scrap are counted, its cycle time grows from 24.8 s to 31.2 s, against a takt of 22.5 s. The largest loss at this step is equipment downtime (uptime 84%), about 4.7 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.