High-Voltage Pyrotechnic Safety Fuse
Product family: 800V Pyro-Disconnect Switches.
Flow: Ceramic fuse & initiator supplier → Copper Busbar Punch → Pyro Squib Crimping & Seal → Arc-Quench Sand Fill & Laser → Micro-Ohm Resistance Scan → X-Ray Squib Bridge Verify → Battery Disconnect Units
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. Copper Busbar Punch | 21.4 s | 55 min | 92% | 97.8% | 2,800 | 4,200 (1.50 d) | 3,267 |
| 2. Pyro Squib Crimping & Seal | 24.6 s | 30 min | 91% | 96.9% | 1,680 | 3,920 (1.40 d) | 2,796 |
| 3. Arc-Quench Sand Fill & Laser | 31.8 s | 20 min | 84% | 94.5% | 3,360 | 7,840 (2.80 d) | 1,997 |
| 4. Micro-Ohm Resistance Scan | 22.6 s | 18 min | 93% | 98.2% | 840 | 2,800 (1.00 d) | 3,128 |
| 5. X-Ray Squib Bridge Verify | 17.4 s | 12 min | 96% | 99.3% | 420 | 1,960 (0.70 d) | 4,175 |
Key figures
- Takt time
- 28.9 s
- Lead time
- 8.60 d
- Value-added time
- 118 s
- Process cycle efficiency (PCE)
- 0.017%
- Rolled throughput yield (RTY)
- 87.3%
- Customer demand per day
- 2,800 parts
- Line capacity per day
- 1,997 parts
- Bottleneck
- Arc-Quench Sand Fill & Laser
Reading the bottleneck
The bottleneck is "Arc-Quench Sand Fill & Laser": it can process 1,997 parts per day against a demand of 2,800 parts, so it falls short of demand by 28.7%. Once downtime and scrap are counted, its cycle time grows from 31.8 s to 40.1 s, against a takt of 28.9 s. The largest loss at this step is equipment downtime (uptime 84%), about 6.1 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of EV Batteries & E-Powertrain: EV Batteries & E-Powertrain
- High-Nickel NMC Prismatic Cell Line
- LFP Cell-to-Pack (CTP) Blade Line
- Vacuum-Brazed Aluminum Battery Cold Plate
- Shielded 800V Orange HV Cable Harness
- 22kW Bi-Directional On-Board Charger
- Automotive ASIL-D Battery Management Controller
- 3kW 800V-to-12V DC-DC Step-Down Unit
- Dual-Standard CCS2 / NACS Motorized Inlet
- 48V Belt-Starter & Lithium Sub-Pack
- Solid-State Oxide Electrolyte Pilot Line
- Standardized Battery-Swap Pack Station