Solid-State Oxide Electrolyte Pilot Line
Product family: Next-Gen Solid-State Cells.
Flow: Ceramic powder supplier → Oxide Tape Cast & Sinter → Lithium Foil Calender → Isostatic Warm Press Stack → Laser Weld Pouch Tab Seal → EIS Impedance Spectroscopy → OEM EV R&D & Pilot Fleet
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. Oxide Tape Cast & Sinter | 111 s | 55 min | 92% | 97.8% | 180 | 270 (1.50 d) | 192 |
| 2. Lithium Foil Calender | 128 s | 30 min | 91% | 96.9% | 108 | 252 (1.40 d) | 165 |
| 3. Isostatic Warm Press Stack | 165 s | 20 min | 84% | 94.5% | 216 | 504 (2.80 d) | 125 |
| 4. Laser Weld Pouch Tab Seal | 117 s | 18 min | 93% | 98.2% | 54 | 180 (1.00 d) | 183 |
| 5. EIS Impedance Spectroscopy | 90.0 s | 12 min | 96% | 99.3% | 27 | 126 (0.70 d) | 235 |
Key figures
- Takt time
- 150 s
- Lead time
- 8.62 d
- Value-added time
- 611 s
- Process cycle efficiency (PCE)
- 0.26%
- Rolled throughput yield (RTY)
- 87.3%
- Customer demand per day
- 180 units
- Line capacity per day
- 125 units
- Bottleneck
- Isostatic Warm Press Stack
Reading the bottleneck
The bottleneck is "Isostatic Warm Press Stack": it can process 125 units per day against a demand of 180 units, so it falls short of demand by 30.5%. Once downtime and scrap are counted, its cycle time grows from 165 s to 208 s, against a takt of 150 s. The largest loss at this step is equipment downtime (uptime 84%), about 31.4 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of EV Batteries & E-Powertrain: EV Batteries & E-Powertrain
- High-Nickel NMC Prismatic Cell Line
- LFP Cell-to-Pack (CTP) Blade Line
- Vacuum-Brazed Aluminum Battery Cold Plate
- Shielded 800V Orange HV Cable Harness
- 22kW Bi-Directional On-Board Charger
- Automotive ASIL-D Battery Management Controller
- 3kW 800V-to-12V DC-DC Step-Down Unit
- Dual-Standard CCS2 / NACS Motorized Inlet
- High-Voltage Pyrotechnic Safety Fuse
- 48V Belt-Starter & Lithium Sub-Pack
- Standardized Battery-Swap Pack Station