Solid-State Oxide Electrolyte Pilot Line

Product family: Next-Gen Solid-State Cells.

Flow: Ceramic powder supplier → Oxide Tape Cast & Sinter → Lithium Foil Calender → Isostatic Warm Press Stack → Laser Weld Pouch Tab Seal → EIS Impedance Spectroscopy → OEM EV R&D & Pilot Fleet

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: Solid-State Oxide Electrolyte Pilot LineSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Ceramic powder supplier → Oxide Tape Cast & Sinter (111 s) → Lithium Foil Calender (128 s) → Isostatic Warm Press Stack (165 s) → Laser Weld Pouch Tab Seal (117 s) → EIS Impedance Spectroscopy (90.0 s) → OEM EV R&D & Pilot Fleet.SUPPLIERCeramic powdersupplierI1.50 d1Oxide Tape Cast &SinterC/T 111 sI1.40 d2Lithium FoilCalenderC/T 128 sI2.80 d3Isostatic WarmPress StackC/T 165 sI1.00 d4Laser Weld PouchTab SealC/T 117 sI0.70 d5EIS ImpedanceSpectroscopyC/T 90.0 sI1.20 dCUSTOMEROEM EV R&D &Pilot Fleet180 / units

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Oxide Tape Cast & Sinter111 s55 min92%97.8%180270 (1.50 d)192
2. Lithium Foil Calender128 s30 min91%96.9%108252 (1.40 d)165
3. Isostatic Warm Press Stack165 s20 min84%94.5%216504 (2.80 d)125
4. Laser Weld Pouch Tab Seal117 s18 min93%98.2%54180 (1.00 d)183
5. EIS Impedance Spectroscopy90.0 s12 min96%99.3%27126 (0.70 d)235

Key figures

Takt time
150 s
Lead time
8.62 d
Value-added time
611 s
Process cycle efficiency (PCE)
0.26%
Rolled throughput yield (RTY)
87.3%
Customer demand per day
180 units
Line capacity per day
125 units
Bottleneck
Isostatic Warm Press Stack

Reading the bottleneck

The bottleneck is "Isostatic Warm Press Stack": it can process 125 units per day against a demand of 180 units, so it falls short of demand by 30.5%. Once downtime and scrap are counted, its cycle time grows from 165 s to 208 s, against a takt of 150 s. The largest loss at this step is equipment downtime (uptime 84%), about 31.4 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.