LFP Cell-to-Pack (CTP) Blade Line

Product family: Structural LFP Battery Packs.

Flow: LFP cell maker → Tray Thermal Paste Dispense → Blade Cell Compression Stack → Side Rail Structural Glue → FPC BMS Busbar Ultrasonic → EOL 400V Charge-Discharge → Mass-Market EV Final Line

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: LFP Cell-to-Pack (CTP) Blade LineSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. LFP cell maker → Tray Thermal Paste Dispense (167 s) → Blade Cell Compression Stack (191 s) → Side Rail Structural Glue (248 s) → FPC BMS Busbar Ultrasonic (176 s) → EOL 400V Charge-Discharge (135 s) → Mass-Market EV Final Line.SUPPLIERLFP cell makerI1.50 d1Tray ThermalPaste DispenseC/T 167 sI1.40 d2Blade CellCompression StackC/T 191 sI2.80 d3Side RailStructural GlueC/T 248 sI1.00 d4FPC BMS BusbarUltrasonicC/T 176 sI0.70 d5EOL 400VCharge-DischargeC/T 135 sI1.20 dCUSTOMERMass-Market EVFinal Line240 / packs

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Tray Thermal Paste Dispense167 s55 min92%97.8%240360 (1.50 d)273
2. Blade Cell Compression Stack191 s30 min91%96.9%144336 (1.40 d)235
3. Side Rail Structural Glue248 s20 min84%94.5%288672 (2.80 d)170
4. FPC BMS Busbar Ultrasonic176 s18 min93%98.2%72240 (1.00 d)262
5. EOL 400V Charge-Discharge135 s12 min96%99.3%36168 (0.70 d)347

Key figures

Takt time
225 s
Lead time
8.62 d
Value-added time
917 s
Process cycle efficiency (PCE)
0.20%
Rolled throughput yield (RTY)
87.3%
Customer demand per day
240 packs
Line capacity per day
170 packs
Bottleneck
Side Rail Structural Glue

Reading the bottleneck

The bottleneck is "Side Rail Structural Glue": it can process 170 packs per day against a demand of 240 packs, so it falls short of demand by 29.3%. Once downtime and scrap are counted, its cycle time grows from 248 s to 312 s, against a takt of 225 s. The largest loss at this step is equipment downtime (uptime 84%), about 47.2 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.