Side Curtain Safety Airbag OPW Module

Product family: Helium-Sealed Rollover Curtains.

Flow: Nylon 6,6 fabric supplier → Silicon Seal Coat & Cure → Laser Pattern Contour Cut → Origami Fold & Sleeve → Hybrid Inflator Crimp Fit → 100% Leak & Squib Ohmic → OEM Trim & Roof Line

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: Side Curtain Safety Airbag OPW ModuleSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Nylon 6,6 fabric supplier → Silicon Seal Coat & Cure (27.8 s) → Laser Pattern Contour Cut (32.4 s) → Origami Fold & Sleeve (41.0 s) → Hybrid Inflator Crimp Fit (29.3 s) → 100% Leak & Squib Ohmic (21.2 s) → OEM Trim & Roof Line.SUPPLIERNylon 6,6fabric supplierI1.40 d1Silicon Seal Coat& CureC/T 27.8 sI1.50 d2Laser PatternContour CutC/T 32.4 sI1.60 d3Origami Fold &SleeveC/T 41.0 sI0.70 d4Hybrid InflatorCrimp FitC/T 29.3 sI0.40 d5100% Leak & SquibOhmicC/T 21.2 sI0.60 dCUSTOMEROEM Trim & RoofLine2,100 / units

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Silicon Seal Coat & Cure27.8 s28 min93%98.1%1,6802,940 (1.40 d)2,589
2. Laser Pattern Contour Cut32.4 s22 min91%96.8%1,0503,150 (1.50 d)2,130
3. Origami Fold & Sleeve41.0 s30 min85%95.5%8403,360 (1.60 d)1,515
4. Hybrid Inflator Crimp Fit29.3 s8 min95%98.7%3151,470 (0.70 d)2,490
5. 100% Leak & Squib Ohmic21.2 s5 min98%99.6%210840 (0.40 d)3,591

Key figures

Takt time
38.6 s
Lead time
6.20 d
Value-added time
152 s
Process cycle efficiency (PCE)
0.030%
Rolled throughput yield (RTY)
89.2%
Customer demand per day
2,100 units
Line capacity per day
1,515 units
Bottleneck
Origami Fold & Sleeve

Reading the bottleneck

The bottleneck is "Origami Fold & Sleeve": it can process 1,515 units per day against a demand of 2,100 units, so it falls short of demand by 27.9%. Once downtime and scrap are counted, its cycle time grows from 41.0 s to 50.5 s, against a takt of 38.6 s. The largest loss at this step is equipment downtime (uptime 85%), about 7.2 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.