Sliding Inductive-Charge Center Console
Product family: Motorized Floor Consoles.
Flow: ABS/PC resin supplier → 2K Twin-Shot Injection → Hard-Coat UV Anti-Scratch → Slide Rail & Motor Mate → Qi Charger & Ambient PCB → Force Curve & Tactile Audit → OEM Interior Line
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. 2K Twin-Shot Injection | 42.0 s | 28 min | 93% | 98.1% | 736 | 1,288 (1.40 d) | 1,127 |
| 2. Hard-Coat UV Anti-Scratch | 49.0 s | 22 min | 91% | 96.8% | 460 | 1,380 (1.50 d) | 923 |
| 3. Slide Rail & Motor Mate | 62.0 s | 30 min | 85% | 95.5% | 368 | 1,472 (1.60 d) | 648 |
| 4. Qi Charger & Ambient PCB | 45.0 s | 8 min | 95% | 98.7% | 138 | 644 (0.70 d) | 1,059 |
| 5. Force Curve & Tactile Audit | 32.3 s | 5 min | 98% | 99.6% | 92 | 368 (0.40 d) | 1,541 |
Key figures
- Takt time
- 58.7 s
- Lead time
- 6.20 d
- Value-added time
- 230 s
- Process cycle efficiency (PCE)
- 0.069%
- Rolled throughput yield (RTY)
- 89.2%
- Customer demand per day
- 920 units
- Line capacity per day
- 648 units
- Bottleneck
- Slide Rail & Motor Mate
Reading the bottleneck
The bottleneck is "Slide Rail & Motor Mate": it can process 648 units per day against a demand of 920 units, so it falls short of demand by 29.6%. Once downtime and scrap are counted, its cycle time grows from 62.0 s to 76.4 s, against a takt of 58.7 s. The largest loss at this step is equipment downtime (uptime 85%), about 10.9 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Interior Trim, Seating & Cockpit: Interior Trim, Seating & Cockpit
- Soft-Touch Slush-Molded Cockpit Assembly
- Ventilated Massage Leather Front Seat
- Ambient-Lit Acoustic Door Trim Panel
- Heated Capacitive Hands-Off Steering Wheel
- Recycled PET Acoustic Modular Headliner
- Multi-Zone EV Heat-Pump Cabin HVAC Unit
- 3D Molded Acoustic Tufted Cabin Carpet
- Drive-by-Wire Organ-Style Pedal Assembly
- Curved Pillar-to-Pillar Glass Display Module
- Side Curtain Safety Airbag OPW Module
- HUD-Grade Acoustic Laminated Windshield