HUD-Grade Acoustic Laminated Windshield

Product family: Solar Coat Curved Glass.

Flow: Float-glass supplier → Laser Diamond Score & Snap → Gravity-Sag Bending Furnace → PVB Cleanroom Interleave → 14-Bar Autoclave Laminate → HUD Optical Wedge & Camera QC → OEM Robot Glazing Bay

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: HUD-Grade Acoustic Laminated WindshieldSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Float-glass supplier → Laser Diamond Score & Snap (49.0 s) → Gravity-Sag Bending Furnace (57.0 s) → PVB Cleanroom Interleave (72.0 s) → 14-Bar Autoclave Laminate (51.0 s) → HUD Optical Wedge & Camera QC (37.1 s) → OEM Robot Glazing Bay.SUPPLIERFloat-glasssupplierI1.40 d1Laser DiamondScore & SnapC/T 49.0 sI1.50 d2Gravity-SagBending FurnaceC/T 57.0 sI1.60 d3PVB CleanroomInterleaveC/T 72.0 sI0.70 d414-Bar AutoclaveLaminateC/T 51.0 sI0.40 d5HUD Optical Wedge& Camera QCC/T 37.1 sI0.60 dCUSTOMEROEM RobotGlazing Bay1,200 / parts

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Laser Diamond Score & Snap49.0 s28 min93%98.1%9601,680 (1.40 d)1,469
2. Gravity-Sag Bending Furnace57.0 s22 min91%96.8%6001,800 (1.50 d)1,211
3. PVB Cleanroom Interleave72.0 s30 min85%95.5%4801,920 (1.60 d)862
4. 14-Bar Autoclave Laminate51.0 s8 min95%98.7%180840 (0.70 d)1,430
5. HUD Optical Wedge & Camera QC37.1 s5 min98%99.6%120480 (0.40 d)2,052

Key figures

Takt time
67.5 s
Lead time
6.20 d
Value-added time
266 s
Process cycle efficiency (PCE)
0.053%
Rolled throughput yield (RTY)
89.2%
Customer demand per day
1,200 parts
Line capacity per day
862 parts
Bottleneck
PVB Cleanroom Interleave

Reading the bottleneck

The bottleneck is "PVB Cleanroom Interleave": it can process 862 parts per day against a demand of 1,200 parts, so it falls short of demand by 28.1%. Once downtime and scrap are counted, its cycle time grows from 72.0 s to 88.7 s, against a takt of 67.5 s. The largest loss at this step is equipment downtime (uptime 85%), about 12.7 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.

Other scenarios in this family

More scenarios of Interior Trim, Seating & Cockpit: Interior Trim, Seating & Cockpit