3D Molded Acoustic Tufted Cabin Carpet

Product family: Heavy-Layer Soundproof Carpets.

Flow: Recycled yarn supplier → Extrude Heavy Barrier Back → Infrared Oven Preheat → Matched Aluminum Cold Press → 5-Axis Waterjet Hole Trim → Footrest Pad Ultrasonic Weld → OEM Under-Seat General Bay

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: 3D Molded Acoustic Tufted Cabin CarpetSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Recycled yarn supplier → Extrude Heavy Barrier Back (41.0 s) → Infrared Oven Preheat (47.0 s) → Matched Aluminum Cold Press (60.0 s) → 5-Axis Waterjet Hole Trim (43.0 s) → Footrest Pad Ultrasonic Weld (30.9 s) → OEM Under-Seat General Bay.SUPPLIERRecycled yarnsupplierI1.40 d1Extrude HeavyBarrier BackC/T 41.0 sI1.50 d2Infrared OvenPreheatC/T 47.0 sI1.60 d3Matched AluminumCold PressC/T 60.0 sI0.70 d45-Axis WaterjetHole TrimC/T 43.0 sI0.40 d5Footrest PadUltrasonic WeldC/T 30.9 sI0.60 dCUSTOMEROEM Under-SeatGeneral Bay960 / parts

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Extrude Heavy Barrier Back41.0 s28 min93%98.1%7681,344 (1.40 d)1,155
2. Infrared Oven Preheat47.0 s22 min91%96.8%4801,440 (1.50 d)963
3. Matched Aluminum Cold Press60.0 s30 min85%95.5%3841,536 (1.60 d)670
4. 5-Axis Waterjet Hole Trim43.0 s8 min95%98.7%144672 (0.70 d)1,108
5. Footrest Pad Ultrasonic Weld30.9 s5 min98%99.6%96384 (0.40 d)1,611

Key figures

Takt time
56.3 s
Lead time
6.20 d
Value-added time
222 s
Process cycle efficiency (PCE)
0.066%
Rolled throughput yield (RTY)
89.2%
Customer demand per day
960 parts
Line capacity per day
670 parts
Bottleneck
Matched Aluminum Cold Press

Reading the bottleneck

The bottleneck is "Matched Aluminum Cold Press": it can process 670 parts per day against a demand of 960 parts, so it falls short of demand by 30.2%. Once downtime and scrap are counted, its cycle time grows from 60.0 s to 73.9 s, against a takt of 56.3 s. The largest loss at this step is equipment downtime (uptime 85%), about 10.6 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.