Sub-Micron Copper Oxychloride Flowable SC
Product family: Wet-Milled Orchard Fungicide.
Flow: Copper Oxychloride Cake → High-Speed Premix Wetting → Zirconia Bead Mill <1.5um → Rheology & Suspendability QC → COEX Barrier 1L/5L Fill → UN Carton Pack & Pallet → Vineyards & Olive Groves
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. High-Speed Premix Wetting | 2.6 s | 30 min | 94% | 98.8% | 21,000 | 22,400 (1.60 d) | 18,860 |
| 2. Zirconia Bead Mill <1.5um | 3.3 s | 45 min | 90% | 97.4% | 21,000 | 25,200 (1.80 d) | 13,866 |
| 3. Rheology & Suspendability QC | 4.1 s | 35 min | 84% | 95.8% | 14,000 | 28,000 (2.00 d) | 10,187 |
| 4. COEX Barrier 1L/5L Fill | 2.8 s | 10 min | 95% | 98.5% | 5,600 | 14,000 (1.00 d) | 17,545 |
| 5. UN Carton Pack & Pallet | 2.2 s | 15 min | 96% | 99.3% | 7,000 | 16,800 (1.20 d) | 22,619 |
Key figures
- Takt time
- 3.9 s
- Lead time
- 9.80 d
- Value-added time
- 15.0 s
- Process cycle efficiency (PCE)
- 0.003%
- Rolled throughput yield (RTY)
- 90.2%
- Customer demand per day
- 14,000 liters
- Line capacity per day
- 10,187 liters
- Bottleneck
- Rheology & Suspendability QC
Reading the bottleneck
The bottleneck is "Rheology & Suspendability QC": it can process 10,187 liters per day against a demand of 14,000 liters, so it falls short of demand by 27.2%. Once downtime and scrap are counted, its cycle time grows from 4.1 s to 5.1 s, against a takt of 3.9 s. The largest loss at this step is equipment downtime (uptime 84%), about 0.8 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Agrochemicals, Fertilizers & Bio-Inputs: Agrochemicals, Fertilizers & Bio-Inputs
- Complex NPK 15-15-15 Pipe-Reactor Granulation
- EDTA / EDDHA Iron Chelated Micro-Granule Plant
- Cold-Extracted Ascophyllum Bio-Stimulant Liquid
- Polymer Film & Inoculant Precision Seed Treater
- Polymer-Coated Controlled-Release Urea Prill
- Two-Part Concentrated Hydroponic A+B Nutrients
- Bt Bacillus Thuringiensis Bio-Insecticide Ferment
- Pelletized Dolomitic Agricultural Soil Lime
- Sanitized 70°C Poultry-Manure Organic Pellet
- Controlled-Release Moth Mating Disruption Lure
- Leonardite Potassium Humate Flake Extraction