Pelletized Dolomitic Agricultural Soil Lime

Product family: Fast-Dissolve Calcium Pellets.

Flow: Dolomite Limestone Quarry → Fine Raymond Mill <100 mesh → Lignosulfonate Binder Pan Mix → Disc Pelletizer Ball Growth → Rotary Belt Dry & Screen → 500kg FIBC Tote Bagging → Acidic Arable Farms

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: Pelletized Dolomitic Agricultural Soil LimeSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Dolomite Limestone Quarry → Fine Raymond Mill <100 mesh (153 s) → Lignosulfonate Binder Pan Mix (191 s) → Disc Pelletizer Ball Growth (239 s) → Rotary Belt Dry & Screen (162 s) → 500kg FIBC Tote Bagging (131 s) → Acidic Arable Farms.SUPPLIERDolomiteLimestoneQuarryI1.60 d1Fine Raymond Mill<100 meshC/T 153 sI1.80 d2LignosulfonateBinder Pan MixC/T 191 sI2.00 d3Disc PelletizerBall GrowthC/T 239 sI1.00 d4Rotary Belt Dry &ScreenC/T 162 sI1.20 d5500kg FIBC ToteBaggingC/T 131 sI2.20 dCUSTOMERAcidic ArableFarms240 / tonnes

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Fine Raymond Mill <100 mesh153 s30 min94%98.8%360384 (1.60 d)320
2. Lignosulfonate Binder Pan Mix191 s45 min90%97.4%360432 (1.80 d)240
3. Disc Pelletizer Ball Growth239 s35 min84%95.8%240480 (2.00 d)175
4. Rotary Belt Dry & Screen162 s10 min95%98.5%96240 (1.00 d)303
5. 500kg FIBC Tote Bagging131 s15 min96%99.3%120288 (1.20 d)380

Key figures

Takt time
225 s
Lead time
9.82 d
Value-added time
876 s
Process cycle efficiency (PCE)
0.17%
Rolled throughput yield (RTY)
90.2%
Customer demand per day
240 tonnes
Line capacity per day
175 tonnes
Bottleneck
Disc Pelletizer Ball Growth

Reading the bottleneck

The bottleneck is "Disc Pelletizer Ball Growth": it can process 175 tonnes per day against a demand of 240 tonnes, so it falls short of demand by 27.2%. Once downtime and scrap are counted, its cycle time grows from 239 s to 297 s, against a takt of 225 s. The largest loss at this step is equipment downtime (uptime 84%), about 45.5 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.

Other scenarios in this family

More scenarios of Agrochemicals, Fertilizers & Bio-Inputs: Agrochemicals, Fertilizers & Bio-Inputs