Complex NPK 15-15-15 Pipe-Reactor Granulation

Product family: Dust-Free Coated Granular NPK.

Flow: Phosphoric Acid, NH3 & MOP → Pipe-Reactor NH3 Reaction → Rotary Ammoniator Granulator → Co-Current Dryer & Cooler → Crushing Mill & Oil/Talc Coat → Bulk Rail & 500kg Big-Bag → National Ag Co-ops

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: Complex NPK 15-15-15 Pipe-Reactor GranulationSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Phosphoric Acid, NH3 & MOP → Pipe-Reactor NH3 Reaction (131 s) → Rotary Ammoniator Granulator (164 s) → Co-Current Dryer & Cooler (204 s) → Crushing Mill & Oil/Talc Coat (139 s) → Bulk Rail & 500kg Big-Bag (112 s) → National Ag Co-ops.SUPPLIERPhosphoricAcid, NH3 & MOPI1.60 d1Pipe-Reactor NH3ReactionC/T 131 sI1.80 d2Rotary AmmoniatorGranulatorC/T 164 sI2.00 d3Co-Current Dryer& CoolerC/T 204 sI1.00 d4Crushing Mill &Oil/Talc CoatC/T 139 sI1.20 d5Bulk Rail & 500kgBig-BagC/T 112 sI2.20 dCUSTOMERNational AgCo-ops420 / tonnes

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Pipe-Reactor NH3 Reaction131 s30 min94%98.8%630672 (1.60 d)566
2. Rotary Ammoniator Granulator164 s45 min90%97.4%630756 (1.80 d)423
3. Co-Current Dryer & Cooler204 s35 min84%95.8%420840 (2.00 d)311
4. Crushing Mill & Oil/Talc Coat139 s10 min95%98.5%168420 (1.00 d)535
5. Bulk Rail & 500kg Big-Bag112 s15 min96%99.3%210504 (1.20 d)674

Key figures

Takt time
193 s
Lead time
9.81 d
Value-added time
750 s
Process cycle efficiency (PCE)
0.094%
Rolled throughput yield (RTY)
90.2%
Customer demand per day
420 tonnes
Line capacity per day
311 tonnes
Bottleneck
Co-Current Dryer & Cooler

Reading the bottleneck

The bottleneck is "Co-Current Dryer & Cooler": it can process 311 tonnes per day against a demand of 420 tonnes, so it falls short of demand by 25.9%. Once downtime and scrap are counted, its cycle time grows from 204 s to 254 s, against a takt of 193 s. The largest loss at this step is equipment downtime (uptime 84%), about 38.9 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.