Polymer-Coated Controlled-Release Urea Prill
Product family: 90-Day Sulfur/PU Slow-Release.
Flow: Prilled Granular Urea 46% → Pre-Heat 75°C Rotary Drum → Multi-Spray MDI/Polyol React → Anti-Static Wax Topcoat → 24h Water Leach Curve Audit → 25kg Bag & Container Bulk → Turf, Rice & Orchard Growers
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. Pre-Heat 75°C Rotary Drum | 648 s | 30 min | 94% | 98.8% | 128 | 136 (1.60 d) | 114 |
| 2. Multi-Spray MDI/Polyol React | 810 s | 45 min | 90% | 97.4% | 128 | 153 (1.80 d) | 86 |
| 3. Anti-Static Wax Topcoat | 1,010 s | 35 min | 84% | 95.8% | 85 | 170 (2.00 d) | 63 |
| 4. 24h Water Leach Curve Audit | 686 s | 10 min | 95% | 98.5% | 34 | 85 (1.00 d) | 108 |
| 5. 25kg Bag & Container Bulk | 553 s | 15 min | 96% | 99.3% | 43 | 102 (1.20 d) | 137 |
Key figures
- Takt time
- 953 s
- Lead time
- 9.85 d
- Value-added time
- 3,707 s
- Process cycle efficiency (PCE)
- 0.46%
- Rolled throughput yield (RTY)
- 90.2%
- Customer demand per day
- 85 tonnes
- Line capacity per day
- 63 tonnes
- Bottleneck
- Anti-Static Wax Topcoat
Reading the bottleneck
The bottleneck is "Anti-Static Wax Topcoat": it can process 63 tonnes per day against a demand of 85 tonnes, so it falls short of demand by 26.0%. Once downtime and scrap are counted, its cycle time grows from 1,010 s to 1,255 s, against a takt of 953 s. The largest loss at this step is equipment downtime (uptime 84%), about 192 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Agrochemicals, Fertilizers & Bio-Inputs: Agrochemicals, Fertilizers & Bio-Inputs
- Complex NPK 15-15-15 Pipe-Reactor Granulation
- EDTA / EDDHA Iron Chelated Micro-Granule Plant
- Cold-Extracted Ascophyllum Bio-Stimulant Liquid
- Polymer Film & Inoculant Precision Seed Treater
- Two-Part Concentrated Hydroponic A+B Nutrients
- Bt Bacillus Thuringiensis Bio-Insecticide Ferment
- Pelletized Dolomitic Agricultural Soil Lime
- Sanitized 70°C Poultry-Manure Organic Pellet
- Controlled-Release Moth Mating Disruption Lure
- Sub-Micron Copper Oxychloride Flowable SC
- Leonardite Potassium Humate Flake Extraction