Bt Bacillus Thuringiensis Bio-Insecticide Ferment

Product family: OMRI Organic Crop Spray.

Flow: Corn Steep Liquor & Spores → 20,000L Aerobic Sporulation → Disc-Stack Centrifuge Harvest → Spray Dry / Flowable Stabilize → Bioassay Caterpillar Potency → 1L & 10L Induction Cap Line → Organic Fruit & Veg Co-ops

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: Bt Bacillus Thuringiensis Bio-Insecticide FermentSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Corn Steep Liquor & Spores → 20,000L Aerobic Sporulation (3.9 s) → Disc-Stack Centrifuge Harvest (4.9 s) → Spray Dry / Flowable Stabilize (6.1 s) → Bioassay Caterpillar Potency (4.2 s) → 1L & 10L Induction Cap Line (3.4 s) → Organic Fruit & Veg Co-ops.SUPPLIERCorn SteepLiquor & SporesI1.60 d120,000L AerobicSporulationC/T 3.9 sI1.80 d2Disc-StackCentrifuge…C/T 4.9 sI2.00 d3Spray Dry /Flowable…C/T 6.1 sI1.00 d4BioassayCaterpillar…C/T 4.2 sI1.20 d51L & 10LInduction Cap…C/T 3.4 sI2.20 dCUSTOMEROrganic Fruit &Veg Co-ops14,000 / liters

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. 20,000L Aerobic Sporulation3.9 s30 min94%98.8%21,00022,400 (1.60 d)19,003
2. Disc-Stack Centrifuge Harvest4.9 s45 min90%97.4%21,00025,200 (1.80 d)14,169
3. Spray Dry / Flowable Stabilize6.1 s35 min84%95.8%14,00028,000 (2.00 d)10,409
4. Bioassay Caterpillar Potency4.2 s10 min95%98.5%5,60014,000 (1.00 d)17,712
5. 1L & 10L Induction Cap Line3.4 s15 min96%99.3%7,00016,800 (1.20 d)22,206

Key figures

Takt time
5.8 s
Lead time
9.80 d
Value-added time
22.5 s
Process cycle efficiency (PCE)
0.003%
Rolled throughput yield (RTY)
90.2%
Customer demand per day
14,000 liters
Line capacity per day
10,409 liters
Bottleneck
Spray Dry / Flowable Stabilize

Reading the bottleneck

The bottleneck is "Spray Dry / Flowable Stabilize": it can process 10,409 liters per day against a demand of 14,000 liters, so it falls short of demand by 25.7%. Once downtime and scrap are counted, its cycle time grows from 6.1 s to 7.6 s, against a takt of 5.8 s. The largest loss at this step is equipment downtime (uptime 84%), about 1.2 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.

Other scenarios in this family

More scenarios of Agrochemicals, Fertilizers & Bio-Inputs: Agrochemicals, Fertilizers & Bio-Inputs