Cold-Extracted Ascophyllum Bio-Stimulant Liquid
Product family: Organic Cytokinin Foliar Jugs.
Flow: North Atlantic Kelp Harvest → Cryo Cell-Burst Micro-Mill → Cold Alkaline/Enzymatic Extract → Centrifuge Clarify & 50um Filt → Organic Humic Standardization → Vent-Cap HDPE 5L Fill Line → High-Value Orchard Growers
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. Cryo Cell-Burst Micro-Mill | 3.1 s | 30 min | 94% | 98.8% | 18,000 | 19,200 (1.60 d) | 15,818 |
| 2. Cold Alkaline/Enzymatic Extract | 3.8 s | 45 min | 90% | 97.4% | 18,000 | 21,600 (1.80 d) | 12,042 |
| 3. Centrifuge Clarify & 50um Filt | 4.8 s | 35 min | 84% | 95.8% | 12,000 | 24,000 (2.00 d) | 8,701 |
| 4. Organic Humic Standardization | 3.2 s | 10 min | 95% | 98.5% | 4,800 | 12,000 (1.00 d) | 15,352 |
| 5. Vent-Cap HDPE 5L Fill Line | 2.6 s | 15 min | 96% | 99.3% | 6,000 | 14,400 (1.20 d) | 19,139 |
Key figures
- Takt time
- 4.5 s
- Lead time
- 9.80 d
- Value-added time
- 17.5 s
- Process cycle efficiency (PCE)
- 0.003%
- Rolled throughput yield (RTY)
- 90.2%
- Customer demand per day
- 12,000 liters
- Line capacity per day
- 8,701 liters
- Bottleneck
- Centrifuge Clarify & 50um Filt
Reading the bottleneck
The bottleneck is "Centrifuge Clarify & 50um Filt": it can process 8,701 liters per day against a demand of 12,000 liters, so it falls short of demand by 27.5%. Once downtime and scrap are counted, its cycle time grows from 4.8 s to 6.0 s, against a takt of 4.5 s. The largest loss at this step is equipment downtime (uptime 84%), about 0.9 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Agrochemicals, Fertilizers & Bio-Inputs: Agrochemicals, Fertilizers & Bio-Inputs
- Complex NPK 15-15-15 Pipe-Reactor Granulation
- EDTA / EDDHA Iron Chelated Micro-Granule Plant
- Polymer Film & Inoculant Precision Seed Treater
- Polymer-Coated Controlled-Release Urea Prill
- Two-Part Concentrated Hydroponic A+B Nutrients
- Bt Bacillus Thuringiensis Bio-Insecticide Ferment
- Pelletized Dolomitic Agricultural Soil Lime
- Sanitized 70°C Poultry-Manure Organic Pellet
- Controlled-Release Moth Mating Disruption Lure
- Sub-Micron Copper Oxychloride Flowable SC
- Leonardite Potassium Humate Flake Extraction