Two-Part Concentrated Hydroponic A+B Nutrients
Product family: EC-Balanced Greenhouse Feeds.
Flow: Technical Calcium Nitrate & MKP → RO Heated Dissolving Tank A/B → Density & Trace ICP Check → 1um Cartridge Polish Filter → Twin-Bottle Synchronous Fill → Pallet Stretch & Batch Spec → Vertical & Glasshouse Farms
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. RO Heated Dissolving Tank A/B | 2.3 s | 30 min | 94% | 98.8% | 24,000 | 25,600 (1.60 d) | 21,320 |
| 2. Density & Trace ICP Check | 2.9 s | 45 min | 90% | 97.4% | 24,000 | 28,800 (1.80 d) | 15,779 |
| 3. 1um Cartridge Polish Filter | 3.6 s | 35 min | 84% | 95.8% | 16,000 | 32,000 (2.00 d) | 11,601 |
| 4. Twin-Bottle Synchronous Fill | 2.4 s | 10 min | 95% | 98.5% | 6,400 | 16,000 (1.00 d) | 20,470 |
| 5. Pallet Stretch & Batch Spec | 2.0 s | 15 min | 96% | 99.3% | 8,000 | 19,200 (1.20 d) | 24,881 |
Key figures
- Takt time
- 3.4 s
- Lead time
- 9.80 d
- Value-added time
- 13.2 s
- Process cycle efficiency (PCE)
- 0.002%
- Rolled throughput yield (RTY)
- 90.2%
- Customer demand per day
- 16,000 liters
- Line capacity per day
- 11,601 liters
- Bottleneck
- 1um Cartridge Polish Filter
Reading the bottleneck
The bottleneck is "1um Cartridge Polish Filter": it can process 11,601 liters per day against a demand of 16,000 liters, so it falls short of demand by 27.5%. Once downtime and scrap are counted, its cycle time grows from 3.6 s to 4.5 s, against a takt of 3.4 s. The largest loss at this step is equipment downtime (uptime 84%), about 0.7 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Agrochemicals, Fertilizers & Bio-Inputs: Agrochemicals, Fertilizers & Bio-Inputs
- Complex NPK 15-15-15 Pipe-Reactor Granulation
- EDTA / EDDHA Iron Chelated Micro-Granule Plant
- Cold-Extracted Ascophyllum Bio-Stimulant Liquid
- Polymer Film & Inoculant Precision Seed Treater
- Polymer-Coated Controlled-Release Urea Prill
- Bt Bacillus Thuringiensis Bio-Insecticide Ferment
- Pelletized Dolomitic Agricultural Soil Lime
- Sanitized 70°C Poultry-Manure Organic Pellet
- Controlled-Release Moth Mating Disruption Lure
- Sub-Micron Copper Oxychloride Flowable SC
- Leonardite Potassium Humate Flake Extraction