Low-VOC Waterborne Matte Emulsion Wall Paint

Product family: 10L Automated Tint-Base Pails.

Flow: Acrylic Emulsion Producer → Automated Liquid Tank Farm → High-Speed Cowles Disperser → In-Can Preservative & Shade → 4-Head Weight Scale Fill/Lid → Robot Label & Euro-Pallet → DIY Big-Box Retail Chains

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: Low-VOC Waterborne Matte Emulsion Wall PaintSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Acrylic Emulsion Producer → Automated Liquid Tank Farm (11.5 s) → High-Speed Cowles Disperser (14.2 s) → In-Can Preservative & Shade (18.1 s) → 4-Head Weight Scale Fill/Lid (12.2 s) → Robot Label & Euro-Pallet (10.1 s) → DIY Big-Box Retail Chains.SUPPLIERAcrylicEmulsionProducerI1.50 d1Automated LiquidTank FarmC/T 11.5 sI1.90 d2High-Speed CowlesDisperserC/T 14.2 sI2.20 d3In-CanPreservative &…C/T 18.1 sI0.90 d44-Head WeightScale Fill/LidC/T 12.2 sI1.00 d5Robot Label &Euro-PalletC/T 10.1 sI1.60 dCUSTOMERDIY Big-BoxRetail Chains3,200 / packs

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Automated Liquid Tank Farm11.5 s25 min94%98.5%4,8004,800 (1.50 d)4,267
2. High-Speed Cowles Disperser14.2 s65 min89%97.2%4,8006,080 (1.90 d)3,131
3. In-Can Preservative & Shade18.1 s20 min84%94.5%3,2007,040 (2.20 d)2,316
4. 4-Head Weight Scale Fill/Lid12.2 s15 min94%98.8%1,6002,880 (0.90 d)3,974
5. Robot Label & Euro-Pallet10.1 s25 min93%99.1%1,6003,200 (1.00 d)4,654

Key figures

Takt time
16.9 s
Lead time
9.10 d
Value-added time
66.1 s
Process cycle efficiency (PCE)
0.013%
Rolled throughput yield (RTY)
88.6%
Customer demand per day
3,200 packs
Line capacity per day
2,316 packs
Bottleneck
In-Can Preservative & Shade

Reading the bottleneck

The bottleneck is "In-Can Preservative & Shade": it can process 2,316 packs per day against a demand of 3,200 packs, so it falls short of demand by 27.6%. Once downtime and scrap are counted, its cycle time grows from 18.1 s to 22.8 s, against a takt of 16.9 s. The largest loss at this step is equipment downtime (uptime 84%), about 3.4 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.