Architectural Super-Durable Polyester Powder

Product family: 25kg Extruded Flake Cartons.

Flow: Polyester Resin Producer → Premix Drum Tumbler Blend → Twin-Screw Melt Knead & Chill → ACM Micro-Grind 35um Air Mill → Gloss & Delta-E Cure Lab → Fluidized Box Bag Packing → Al Facade Extruders

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: Architectural Super-Durable Polyester PowderSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Polyester Resin Producer → Premix Drum Tumbler Blend (765 s) → Twin-Screw Melt Knead & Chill (945 s) → ACM Micro-Grind 35um Air Mill (1,204 s) → Gloss & Delta-E Cure Lab (810 s) → Fluidized Box Bag Packing (675 s) → Al Facade Extruders.SUPPLIERPolyester ResinProducerI1.50 d1Premix DrumTumbler BlendC/T 765 sI1.90 d2Twin-Screw MeltKnead & ChillC/T 945 sI2.21 d3ACM Micro-Grind35um Air MillC/T 1,204 sI0.90 d4Gloss & Delta-ECure LabC/T 810 sI1.00 d5Fluidized Box BagPackingC/T 675 sI1.60 dCUSTOMERAl FacadeExtruders48 / tonnes

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Premix Drum Tumbler Blend765 s25 min94%98.5%7272 (1.50 d)64
2. Twin-Screw Melt Knead & Chill945 s65 min89%97.2%7291 (1.90 d)47
3. ACM Micro-Grind 35um Air Mill1,204 s20 min84%94.5%48106 (2.21 d)35
4. Gloss & Delta-E Cure Lab810 s15 min94%98.8%2443 (0.90 d)60
5. Fluidized Box Bag Packing675 s25 min93%99.1%2448 (1.00 d)70

Key figures

Takt time
1,125 s
Lead time
9.19 d
Value-added time
4,399 s
Process cycle efficiency (PCE)
0.89%
Rolled throughput yield (RTY)
88.6%
Customer demand per day
48 tonnes
Line capacity per day
35 tonnes
Bottleneck
ACM Micro-Grind 35um Air Mill

Reading the bottleneck

The bottleneck is "ACM Micro-Grind 35um Air Mill": it can process 35 tonnes per day against a demand of 48 tonnes, so it falls short of demand by 27.5%. Once downtime and scrap are counted, its cycle time grows from 1,204 s to 1,517 s, against a takt of 1,125 s. The largest loss at this step is equipment downtime (uptime 84%), about 229 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.