Precision Color-Matched Touch-Up Aerosol Can

Product family: 400mL DME Propellant Sprays.

Flow: Aerosol Can Supplier → Automated Gravimetric Tint Mix → Glass Marbles & Paint Dose → Valve Crimp & DME Gas Charge → Hot Water Tank & Spray Print → Color Cap Match & Tray Box → Automotive DIY & Bodyshops

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: Precision Color-Matched Touch-Up Aerosol CanSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Aerosol Can Supplier → Automated Gravimetric Tint Mix (2.6 s) → Glass Marbles & Paint Dose (3.2 s) → Valve Crimp & DME Gas Charge (4.1 s) → Hot Water Tank & Spray Print (2.8 s) → Color Cap Match & Tray Box (2.3 s) → Automotive DIY & Bodyshops.SUPPLIERAerosol CanSupplierI1.50 d1AutomatedGravimetric Tint…C/T 2.6 sI1.90 d2Glass Marbles &Paint DoseC/T 3.2 sI2.20 d3Valve Crimp & DMEGas ChargeC/T 4.1 sI0.90 d4Hot Water Tank &Spray PrintC/T 2.8 sI1.00 d5Color Cap Match &Tray BoxC/T 2.3 sI1.60 dCUSTOMERAutomotive DIY& Bodyshops14,000 / packs

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Automated Gravimetric Tint Mix2.6 s25 min94%98.5%21,00021,000 (1.50 d)18,874
2. Glass Marbles & Paint Dose3.2 s65 min89%97.2%21,00026,600 (1.90 d)13,895
3. Valve Crimp & DME Gas Charge4.1 s20 min84%94.5%14,00030,800 (2.20 d)10,223
4. Hot Water Tank & Spray Print2.8 s15 min94%98.8%7,00012,600 (0.90 d)17,314
5. Color Cap Match & Tray Box2.3 s25 min93%99.1%7,00014,000 (1.00 d)20,436

Key figures

Takt time
3.9 s
Lead time
9.10 d
Value-added time
15.0 s
Process cycle efficiency (PCE)
0.003%
Rolled throughput yield (RTY)
88.6%
Customer demand per day
14,000 packs
Line capacity per day
10,223 packs
Bottleneck
Valve Crimp & DME Gas Charge

Reading the bottleneck

The bottleneck is "Valve Crimp & DME Gas Charge": it can process 10,223 packs per day against a demand of 14,000 packs, so it falls short of demand by 27.0%. Once downtime and scrap are counted, its cycle time grows from 4.1 s to 5.2 s, against a takt of 3.9 s. The largest loss at this step is equipment downtime (uptime 84%), about 0.8 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.