Specialty Coatings Batch Mixing & Fill

Product family: 20L Epoxy Industrial Coatings.

Flow: Pigment & TiO2 Mineral Supplier → Solvent & Resin Dosing → Dispersion & Letdown → Lab Shade & Viscosity QC → Fine Micron Bag Filter → Filtered Drum Filling → Marine & Infra Contractors

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: Specialty Coatings Batch Mixing & FillSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Pigment & TiO2 Mineral Supplier → Solvent & Resin Dosing (61.0 s) → Dispersion & Letdown (76.0 s) → Lab Shade & Viscosity QC (96.0 s) → Fine Micron Bag Filter (65.0 s) → Filtered Drum Filling (54.0 s) → Marine & Infra Contractors.SUPPLIERPigment & TiO2MineralSupplierI1.50 d1Solvent & ResinDosingC/T 61.0 sI1.90 d2Dispersion &LetdownC/T 76.0 sI2.20 d3Lab Shade &Viscosity QCC/T 96.0 sI0.90 d4Fine Micron BagFilterC/T 65.0 sI1.00 d5Filtered DrumFillingC/T 54.0 sI1.60 dCUSTOMERMarine & InfraContractors600 / liters

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Solvent & Resin Dosing61.0 s25 min94%98.5%900900 (1.50 d)804
2. Dispersion & Letdown76.0 s65 min89%97.2%9001,140 (1.90 d)585
3. Lab Shade & Viscosity QC96.0 s20 min84%94.5%6001,320 (2.20 d)437
4. Fine Micron Bag Filter65.0 s15 min94%98.8%300540 (0.90 d)746
5. Filtered Drum Filling54.0 s25 min93%99.1%300600 (1.00 d)870

Key figures

Takt time
90.0 s
Lead time
9.11 d
Value-added time
352 s
Process cycle efficiency (PCE)
0.072%
Rolled throughput yield (RTY)
88.6%
Customer demand per day
600 liters
Line capacity per day
437 liters
Bottleneck
Lab Shade & Viscosity QC

Reading the bottleneck

The bottleneck is "Lab Shade & Viscosity QC": it can process 437 liters per day against a demand of 600 liters, so it falls short of demand by 27.2%. Once downtime and scrap are counted, its cycle time grows from 96.0 s to 121 s, against a takt of 90.0 s. The largest loss at this step is equipment downtime (uptime 84%), about 18.3 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.