Silicone Foul-Release Copper-Free Marine Hull

Product family: Zero-Biocide Silicone Paint.

Flow: Silicone Polymer Producer → Moisture-Free Vacuum Knead → Bead Mill Fineness <15um → Moisture Trace & Viscosity Lab → Dry Nitrogen Drum Headspace → Slip-Angle Hydro Panel Audit → Global Commercial Shipyards

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: Silicone Foul-Release Copper-Free Marine HullSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Silicone Polymer Producer → Moisture-Free Vacuum Knead (153 s) → Bead Mill Fineness <15um (189 s) → Moisture Trace & Viscosity Lab (241 s) → Dry Nitrogen Drum Headspace (162 s) → Slip-Angle Hydro Panel Audit (135 s) → Global Commercial Shipyards.SUPPLIERSiliconePolymerProducerI1.50 d1Moisture-FreeVacuum KneadC/T 153 sI1.90 d2Bead MillFineness <15umC/T 189 sI2.20 d3Moisture Trace &Viscosity LabC/T 241 sI0.90 d4Dry Nitrogen DrumHeadspaceC/T 162 sI1.00 d5Slip-Angle HydroPanel AuditC/T 135 sI1.60 dCUSTOMERGlobalCommercial…240 / packs

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Moisture-Free Vacuum Knead153 s25 min94%98.5%360360 (1.50 d)321
2. Bead Mill Fineness <15um189 s65 min89%97.2%360456 (1.90 d)235
3. Moisture Trace & Viscosity Lab241 s20 min84%94.5%240528 (2.20 d)174
4. Dry Nitrogen Drum Headspace162 s15 min94%98.8%120216 (0.90 d)299
5. Slip-Angle Hydro Panel Audit135 s25 min93%99.1%120240 (1.00 d)348

Key figures

Takt time
225 s
Lead time
9.12 d
Value-added time
880 s
Process cycle efficiency (PCE)
0.18%
Rolled throughput yield (RTY)
88.6%
Customer demand per day
240 packs
Line capacity per day
174 packs
Bottleneck
Moisture Trace & Viscosity Lab

Reading the bottleneck

The bottleneck is "Moisture Trace & Viscosity Lab": it can process 174 packs per day against a demand of 240 packs, so it falls short of demand by 27.5%. Once downtime and scrap are counted, its cycle time grows from 241 s to 304 s, against a takt of 225 s. The largest loss at this step is equipment downtime (uptime 84%), about 45.9 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.