High-Build Glass-Bead Reflective Road Paint

Product family: Cold-Plastic Highway Markings.

Flow: Glass Microsphere Supplier → MMA Reactor Blend Dispersion → Reflective Skid Grit Loading → Lab Drying Time & Luminance → Steel Open-Head Drum Fill → ADR Placard Palletizing → Highway Civil Contractors

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: High-Build Glass-Bead Reflective Road PaintSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Glass Microsphere Supplier → MMA Reactor Blend Dispersion (668 s) → Reflective Skid Grit Loading (825 s) → Lab Drying Time & Luminance (1,051 s) → Steel Open-Head Drum Fill (707 s) → ADR Placard Palletizing (589 s) → Highway Civil Contractors.SUPPLIERGlassMicrosphereSupplierI1.51 d1MMA Reactor BlendDispersionC/T 668 sI1.91 d2Reflective SkidGrit LoadingC/T 825 sI2.20 d3Lab Drying Time &LuminanceC/T 1,051 sI0.91 d4Steel Open-HeadDrum FillC/T 707 sI1.00 d5ADR PlacardPalletizingC/T 589 sI1.60 dCUSTOMERHighway CivilContractors55 / tonnes

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. MMA Reactor Blend Dispersion668 s25 min94%98.5%8383 (1.51 d)73
2. Reflective Skid Grit Loading825 s65 min89%97.2%83105 (1.91 d)54
3. Lab Drying Time & Luminance1,051 s20 min84%94.5%55121 (2.20 d)40
4. Steel Open-Head Drum Fill707 s15 min94%98.8%2850 (0.91 d)69
5. ADR Placard Palletizing589 s25 min93%99.1%2855 (1.00 d)80

Key figures

Takt time
982 s
Lead time
9.20 d
Value-added time
3,840 s
Process cycle efficiency (PCE)
0.77%
Rolled throughput yield (RTY)
88.6%
Customer demand per day
55 tonnes
Line capacity per day
40 tonnes
Bottleneck
Lab Drying Time & Luminance

Reading the bottleneck

The bottleneck is "Lab Drying Time & Luminance": it can process 40 tonnes per day against a demand of 55 tonnes, so it falls short of demand by 27.5%. Once downtime and scrap are counted, its cycle time grows from 1,051 s to 1,324 s, against a takt of 982 s. The largest loss at this step is equipment downtime (uptime 84%), about 200 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.