ISO 22241 Ultra-Pure AdBlue / DEF Tote Line

Product family: 32.5% Urea SCR Solution.

Flow: Technical Prilled Urea Producer → 18-Megaohm Ultrapure Dissolve → Activated Carbon & 1um Filter → Refractometer & Biuret Lab → Dedicated PP Nozzle Tote Fill → Batch ISO-22241 Seal Tag → Truck Stops & Fleets

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: ISO 22241 Ultra-Pure AdBlue / DEF Tote LineSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Technical Prilled Urea Producer → 18-Megaohm Ultrapure Dissolve (1.2 s) → Activated Carbon & 1um Filter (1.6 s) → Refractometer & Biuret Lab (2.0 s) → Dedicated PP Nozzle Tote Fill (1.5 s) → Batch ISO-22241 Seal Tag (1.2 s) → Truck Stops & Fleets.SUPPLIERTechnicalPrilled UreaProducerI1.40 d118-MegaohmUltrapure…C/T 1.2 sI1.60 d2Activated Carbon& 1um FilterC/T 1.6 sI2.00 d3Refractometer &Biuret LabC/T 2.0 sI1.10 d4Dedicated PPNozzle Tote FillC/T 1.5 sI0.90 d5Batch ISO-22241Seal TagC/T 1.2 sI1.50 dCUSTOMERTruck Stops &Fleets42,000 / liters

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. 18-Megaohm Ultrapure Dissolve1.2 s20 min95%99.1%63,00058,800 (1.40 d)62,920
2. Activated Carbon & 1um Filter1.6 s45 min91%98.2%50,40067,200 (1.60 d)43,983
3. Refractometer & Biuret Lab2.0 s18 min85%95.8%42,00084,000 (2.00 d)32,539
4. Dedicated PP Nozzle Tote Fill1.5 s30 min92%98.4%25,20046,200 (1.10 d)47,075
5. Batch ISO-22241 Seal Tag1.2 s10 min97%99.5%16,80037,800 (0.90 d)63,941

Key figures

Takt time
1.9 s
Lead time
8.50 d
Value-added time
7.5 s
Process cycle efficiency (PCE)
0.001%
Rolled throughput yield (RTY)
91.3%
Customer demand per day
42,000 liters
Line capacity per day
32,539 liters
Bottleneck
Refractometer & Biuret Lab

Reading the bottleneck

The bottleneck is "Refractometer & Biuret Lab": it can process 32,539 liters per day against a demand of 42,000 liters, so it falls short of demand by 22.5%. Once downtime and scrap are counted, its cycle time grows from 2.0 s to 2.5 s, against a takt of 1.9 s. The largest loss at this step is equipment downtime (uptime 85%), about 0.4 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.