Neutral-Cure Oxime Silicone Sealant Cartridge
Product family: 310mL Window Glazing Tubes.
Flow: OH-Polymer & Silica Supplier → Planetary Vacuum Kneading → Static Mixer Catalyst Color → Lab Skin-Over & Shore A QC → Automated Tube Fill & Plunger → 12-Pack Display Carton Box → Construction & Hardware
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. Planetary Vacuum Kneading | 1.2 s | 20 min | 95% | 99.1% | 48,000 | 44,800 (1.40 d) | 41,738 |
| 2. Static Mixer Catalyst Color | 1.4 s | 45 min | 91% | 98.2% | 38,400 | 51,200 (1.60 d) | 33,032 |
| 3. Lab Skin-Over & Shore A QC | 1.8 s | 18 min | 85% | 95.8% | 32,000 | 64,000 (2.00 d) | 23,940 |
| 4. Automated Tube Fill & Plunger | 1.3 s | 30 min | 92% | 98.4% | 19,200 | 35,200 (1.10 d) | 35,515 |
| 5. 12-Pack Display Carton Box | 1.2 s | 10 min | 97% | 99.5% | 12,800 | 28,800 (0.90 d) | 42,225 |
Key figures
- Takt time
- 1.7 s
- Lead time
- 8.50 d
- Value-added time
- 6.9 s
- Process cycle efficiency (PCE)
- 0.002%
- Rolled throughput yield (RTY)
- 91.3%
- Customer demand per day
- 32,000 units
- Line capacity per day
- 23,940 units
- Bottleneck
- Lab Skin-Over & Shore A QC
Reading the bottleneck
The bottleneck is "Lab Skin-Over & Shore A QC": it can process 23,940 units per day against a demand of 32,000 units, so it falls short of demand by 25.2%. Once downtime and scrap are counted, its cycle time grows from 1.8 s to 2.2 s, against a takt of 1.7 s. The largest loss at this step is equipment downtime (uptime 85%), about 0.3 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Lubricants, Adhesives & Petrochem: Lubricants, Adhesives & Petrochem
- 0W-20 Full-Synthetic Motor Oil Blending & Pack
- Long-Life OAT EV Thermal Coolant Tote Line
- ISO 22241 Ultra-Pure AdBlue / DEF Tote Line
- Falling-Film SO3 Sulfonation SLES Surfactant
- Metallocene EVA/PO Hot-Melt Packaging Pellets
- Complex Lithium NLGI-2 Bearing Grease Kettle
- NAS-6 Ultra-Clean Zinc-Free Hydraulic Fluid
- SAE Type-IV Aircraft Wing Anti-Icing Fluid
- Inverse Emulsion Polyacrylamide Flocculant
- EFSA Food-Contact Bottle-to-Bottle rPET Pellet
- Hydrophilic Amino-Silicone Textile Softener