EFSA Food-Contact Bottle-to-Bottle rPET Pellet
Product family: Super-Cleaned SSP Resin.
Flow: Post-Consumer Baled Bottles → De-Bale, Hot Caustic Wash → Optical Flake Laser Sort → Twin-Screw Vacuum Extrude → 24h Nitrogen SSP Reactor → Intrinsic Viscosity IV & Benzene → Beverage Bottling Preform
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. De-Bale, Hot Caustic Wash | 546 s | 20 min | 95% | 99.1% | 143 | 133 (1.40 d) | 138 |
| 2. Optical Flake Laser Sort | 716 s | 45 min | 91% | 98.2% | 114 | 152 (1.60 d) | 98 |
| 3. Twin-Screw Vacuum Extrude | 904 s | 18 min | 85% | 95.8% | 95 | 190 (2.00 d) | 72 |
| 4. 24h Nitrogen SSP Reactor | 665 s | 30 min | 92% | 98.4% | 57 | 105 (1.11 d) | 106 |
| 5. Intrinsic Viscosity IV & Benzene | 477 s | 10 min | 97% | 99.5% | 38 | 86 (0.91 d) | 161 |
Key figures
- Takt time
- 853 s
- Lead time
- 8.56 d
- Value-added time
- 3,308 s
- Process cycle efficiency (PCE)
- 0.48%
- Rolled throughput yield (RTY)
- 91.3%
- Customer demand per day
- 95 tonnes
- Line capacity per day
- 72 tonnes
- Bottleneck
- Twin-Screw Vacuum Extrude
Reading the bottleneck
The bottleneck is "Twin-Screw Vacuum Extrude": it can process 72 tonnes per day against a demand of 95 tonnes, so it falls short of demand by 24.2%. Once downtime and scrap are counted, its cycle time grows from 904 s to 1,110 s, against a takt of 853 s. The largest loss at this step is equipment downtime (uptime 85%), about 160 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Lubricants, Adhesives & Petrochem: Lubricants, Adhesives & Petrochem
- 0W-20 Full-Synthetic Motor Oil Blending & Pack
- Long-Life OAT EV Thermal Coolant Tote Line
- ISO 22241 Ultra-Pure AdBlue / DEF Tote Line
- Neutral-Cure Oxime Silicone Sealant Cartridge
- Falling-Film SO3 Sulfonation SLES Surfactant
- Metallocene EVA/PO Hot-Melt Packaging Pellets
- Complex Lithium NLGI-2 Bearing Grease Kettle
- NAS-6 Ultra-Clean Zinc-Free Hydraulic Fluid
- SAE Type-IV Aircraft Wing Anti-Icing Fluid
- Inverse Emulsion Polyacrylamide Flocculant
- Hydrophilic Amino-Silicone Textile Softener