NAS-6 Ultra-Clean Zinc-Free Hydraulic Fluid
Product family: ISO-VG46 Particle-Controlled.
Flow: Hydrocracked Group III Base → Dehumidified Tank Blending → 0.5um Absolute Electrostatic → Optical Laser Particle Count → Clean-Flushed Steel Drum Fill → Sealed Tamper Bung Tag → Excavator & Aerospace Plants
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. Dehumidified Tank Blending | 1.6 s | 20 min | 95% | 99.1% | 33,000 | 30,800 (1.40 d) | 31,303 |
| 2. 0.5um Absolute Electrostatic | 2.1 s | 45 min | 91% | 98.2% | 26,400 | 35,200 (1.60 d) | 22,021 |
| 3. Optical Laser Particle Count | 2.6 s | 18 min | 85% | 95.8% | 22,000 | 44,000 (2.00 d) | 16,574 |
| 4. Clean-Flushed Steel Drum Fill | 1.9 s | 30 min | 92% | 98.4% | 13,200 | 24,200 (1.10 d) | 24,300 |
| 5. Sealed Tamper Bung Tag | 1.4 s | 10 min | 97% | 99.5% | 8,800 | 19,800 (0.90 d) | 36,193 |
Key figures
- Takt time
- 2.5 s
- Lead time
- 8.50 d
- Value-added time
- 9.6 s
- Process cycle efficiency (PCE)
- 0.002%
- Rolled throughput yield (RTY)
- 91.3%
- Customer demand per day
- 22,000 liters
- Line capacity per day
- 16,574 liters
- Bottleneck
- Optical Laser Particle Count
Reading the bottleneck
The bottleneck is "Optical Laser Particle Count": it can process 16,574 liters per day against a demand of 22,000 liters, so it falls short of demand by 24.7%. Once downtime and scrap are counted, its cycle time grows from 2.6 s to 3.2 s, against a takt of 2.5 s. The largest loss at this step is equipment downtime (uptime 85%), about 0.5 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Lubricants, Adhesives & Petrochem: Lubricants, Adhesives & Petrochem
- 0W-20 Full-Synthetic Motor Oil Blending & Pack
- Long-Life OAT EV Thermal Coolant Tote Line
- ISO 22241 Ultra-Pure AdBlue / DEF Tote Line
- Neutral-Cure Oxime Silicone Sealant Cartridge
- Falling-Film SO3 Sulfonation SLES Surfactant
- Metallocene EVA/PO Hot-Melt Packaging Pellets
- Complex Lithium NLGI-2 Bearing Grease Kettle
- SAE Type-IV Aircraft Wing Anti-Icing Fluid
- Inverse Emulsion Polyacrylamide Flocculant
- EFSA Food-Contact Bottle-to-Bottle rPET Pellet
- Hydrophilic Amino-Silicone Textile Softener