SAE Type-IV Aircraft Wing Anti-Icing Fluid
Product family: Emerald Glycol-Thickener Fluid.
Flow: Propylene Glycol Producer → High-Shear Polymer Hydration → Viscosity Shear-Thinning Hold → Aerodynamic Wind Tunnel Audit → Dedicated Tanker Cert Fill → Airport Glycol Hydrant Drop → International Airport Depots
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. High-Shear Polymer Hydration | 1.5 s | 20 min | 95% | 99.1% | 52,500 | 49,000 (1.40 d) | 50,336 |
| 2. Viscosity Shear-Thinning Hold | 1.9 s | 45 min | 91% | 98.2% | 42,000 | 56,000 (1.60 d) | 37,038 |
| 3. Aerodynamic Wind Tunnel Audit | 2.5 s | 18 min | 85% | 95.8% | 35,000 | 70,000 (2.00 d) | 26,032 |
| 4. Dedicated Tanker Cert Fill | 1.8 s | 30 min | 92% | 98.4% | 21,000 | 38,500 (1.10 d) | 39,229 |
| 5. Airport Glycol Hydrant Drop | 1.3 s | 10 min | 97% | 99.5% | 14,000 | 31,500 (0.90 d) | 59,023 |
Key figures
- Takt time
- 2.3 s
- Lead time
- 8.50 d
- Value-added time
- 9.0 s
- Process cycle efficiency (PCE)
- 0.001%
- Rolled throughput yield (RTY)
- 91.3%
- Customer demand per day
- 35,000 liters
- Line capacity per day
- 26,032 liters
- Bottleneck
- Aerodynamic Wind Tunnel Audit
Reading the bottleneck
The bottleneck is "Aerodynamic Wind Tunnel Audit": it can process 26,032 liters per day against a demand of 35,000 liters, so it falls short of demand by 25.6%. Once downtime and scrap are counted, its cycle time grows from 2.5 s to 3.1 s, against a takt of 2.3 s. The largest loss at this step is equipment downtime (uptime 85%), about 0.4 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Lubricants, Adhesives & Petrochem: Lubricants, Adhesives & Petrochem
- 0W-20 Full-Synthetic Motor Oil Blending & Pack
- Long-Life OAT EV Thermal Coolant Tote Line
- ISO 22241 Ultra-Pure AdBlue / DEF Tote Line
- Neutral-Cure Oxime Silicone Sealant Cartridge
- Falling-Film SO3 Sulfonation SLES Surfactant
- Metallocene EVA/PO Hot-Melt Packaging Pellets
- Complex Lithium NLGI-2 Bearing Grease Kettle
- NAS-6 Ultra-Clean Zinc-Free Hydraulic Fluid
- Inverse Emulsion Polyacrylamide Flocculant
- EFSA Food-Contact Bottle-to-Bottle rPET Pellet
- Hydrophilic Amino-Silicone Textile Softener