Falling-Film SO3 Sulfonation SLES Surfactant

Product family: 70% Active Active Wash Paste.

Flow: Oleochemical Fatty Alcohols → Sulfur Burn & Catalytic SO3 → Multi-Tube Falling Film React → Degas, Neutralize & Bleaching → Dioxane <10ppm GC Verify → Heated ISO Tanker Loadout → Detergent & Cosmetics Plants

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: Falling-Film SO3 Sulfonation SLES SurfactantSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Oleochemical Fatty Alcohols → Sulfur Burn & Catalytic SO3 (471 s) → Multi-Tube Falling Film React (619 s) → Degas, Neutralize & Bleaching (781 s) → Dioxane <10ppm GC Verify (574 s) → Heated ISO Tanker Loadout (412 s) → Detergent & Cosmetics Plants.SUPPLIEROleochemicalFatty AlcoholsI1.40 d1Sulfur Burn &Catalytic SO3C/T 471 sI1.60 d2Multi-TubeFalling Film…C/T 619 sI2.00 d3Degas, Neutralize& BleachingC/T 781 sI1.10 d4Dioxane <10ppm GCVerifyC/T 574 sI0.90 d5Heated ISO TankerLoadoutC/T 412 sI1.50 dCUSTOMERDetergent &Cosmetics…110 / tonnes

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Sulfur Burn & Catalytic SO3471 s20 min95%99.1%165154 (1.40 d)160
2. Multi-Tube Falling Film React619 s45 min91%98.2%132176 (1.60 d)114
3. Degas, Neutralize & Bleaching781 s18 min85%95.8%110220 (2.00 d)83
4. Dioxane <10ppm GC Verify574 s30 min92%98.4%66121 (1.10 d)123
5. Heated ISO Tanker Loadout412 s10 min97%99.5%4499 (0.90 d)186

Key figures

Takt time
736 s
Lead time
8.54 d
Value-added time
2,857 s
Process cycle efficiency (PCE)
0.41%
Rolled throughput yield (RTY)
91.3%
Customer demand per day
110 tonnes
Line capacity per day
83 tonnes
Bottleneck
Degas, Neutralize & Bleaching

Reading the bottleneck

The bottleneck is "Degas, Neutralize & Bleaching": it can process 83 tonnes per day against a demand of 110 tonnes, so it falls short of demand by 24.2%. Once downtime and scrap are counted, its cycle time grows from 781 s to 959 s, against a takt of 736 s. The largest loss at this step is equipment downtime (uptime 85%), about 138 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.