Long-Life OAT EV Thermal Coolant Tote Line

Product family: 1000L IBC & 5L Bottles.

Flow: Regional MEG & Deionized Water → DI Water & OAT Salt Premix → Inline Conductivity Blend → Lab pH & Freeze-Point Hold → Mass-Flow IBC / Jug Filling → Tamper Seal & UN Palletizing → EV & ICE OEMs

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: Long-Life OAT EV Thermal Coolant Tote LineSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Regional MEG & Deionized Water → DI Water & OAT Salt Premix (1.9 s) → Inline Conductivity Blend (2.5 s) → Lab pH & Freeze-Point Hold (3.2 s) → Mass-Flow IBC / Jug Filling (2.3 s) → Tamper Seal & UN Palletizing (1.7 s) → EV & ICE OEMs.SUPPLIERRegional MEG &Deionized WaterI1.40 d1DI Water & OATSalt PremixC/T 1.9 sI1.60 d2InlineConductivity…C/T 2.5 sI2.00 d3Lab pH &Freeze-Point HoldC/T 3.2 sI1.10 d4Mass-Flow IBC /Jug FillingC/T 2.3 sI0.90 d5Tamper Seal & UNPalletizingC/T 1.7 sI1.50 dCUSTOMEREV & ICE OEMs18,000 / liters

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. DI Water & OAT Salt Premix1.9 s20 min95%99.1%27,00025,200 (1.40 d)26,361
2. Inline Conductivity Blend2.5 s45 min91%98.2%21,60028,800 (1.60 d)18,498
3. Lab pH & Freeze-Point Hold3.2 s18 min85%95.8%18,00036,000 (2.00 d)13,466
4. Mass-Flow IBC / Jug Filling2.3 s30 min92%98.4%10,80019,800 (1.10 d)20,074
5. Tamper Seal & UN Palletizing1.7 s10 min97%99.5%7,20016,200 (0.90 d)29,806

Key figures

Takt time
3.0 s
Lead time
8.50 d
Value-added time
11.6 s
Process cycle efficiency (PCE)
0.003%
Rolled throughput yield (RTY)
91.3%
Customer demand per day
18,000 liters
Line capacity per day
13,466 liters
Bottleneck
Lab pH & Freeze-Point Hold

Reading the bottleneck

The bottleneck is "Lab pH & Freeze-Point Hold": it can process 13,466 liters per day against a demand of 18,000 liters, so it falls short of demand by 25.2%. Once downtime and scrap are counted, its cycle time grows from 3.2 s to 3.9 s, against a takt of 3.0 s. The largest loss at this step is equipment downtime (uptime 85%), about 0.6 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.