High-Rise Acoustic Double-Board Drywall Train
Product family: 5-Day Zone Partition Cycle.
Flow: Gypsum Board & Mineral Wool → Forklift Board Stock-to-Zone → Galv Stud Track & Frame → MEP Side-1 & Acoustic Wool → Side-2 Boarding & Q3 Skim Tape → Laser Flatness & Dust Clean → Hospital & Tower Fit-Outs
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. Forklift Board Stock-to-Zone | 372 s | 10 min | 96% | 98.4% | 18 | 45 (1.00 d) | 65 |
| 2. Galv Stud Track & Frame | 468 s | 12 min | 93% | 97.6% | 14 | 59 (1.31 d) | 48 |
| 3. MEP Side-1 & Acoustic Wool | 642 s | 20 min | 85% | 93.8% | 14 | 81 (1.80 d) | 29 |
| 4. Side-2 Boarding & Q3 Skim Tape | 444 s | 8 min | 95% | 97.4% | 9 | 41 (0.91 d) | 51 |
| 5. Laser Flatness & Dust Clean | 312 s | 5 min | 97% | 98.8% | 7 | 23 (0.51 d) | 77 |
Key figures
- Takt time
- 600 s
- Lead time
- 6.22 d
- Value-added time
- 2,238 s
- Process cycle efficiency (PCE)
- 1.3%
- Rolled throughput yield (RTY)
- 86.7%
- Customer demand per day
- 45 rooms
- Line capacity per day
- 29 rooms
- Bottleneck
- MEP Side-1 & Acoustic Wool
Reading the bottleneck
The bottleneck is "MEP Side-1 & Acoustic Wool": it can process 29 rooms per day against a demand of 45 rooms, so it falls short of demand by 36.1%. Once downtime and scrap are counted, its cycle time grows from 642 s to 805 s, against a takt of 600 s. The largest loss at this step is equipment downtime (uptime 85%), about 113 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Commercial Building MEP & Fit-Out Trades: Commercial Building MEP & Fit-Out Trades
- Grade-A Office Tower Floor MEP First-Fix Takt
- Bio-Pharma Cleanroom Stainless Exhaust Ducting
- Warehouse ESFR High-Hazard Fire Sprinkler Grid
- Food & Pharma Seamless Polyurethane Screed Floor
- 10m/s Gearless High-Rise Elevator Shaft Install
- Smart Building BACnet / KNX HVAC Commissioning
- 500kW Commercial Flat-Roof Ballasted Solar Fit
- Industrial Refinery Turnaround Scaffold Build
- Multi-Tier Heavy Warehouse Steel Mezzanine
- Frameless Acoustic Office Glass Partitioning
- 70-Meter Internal Climbing Tower Crane Erection