High-Rise Acoustic Double-Board Drywall Train

Product family: 5-Day Zone Partition Cycle.

Flow: Gypsum Board & Mineral Wool → Forklift Board Stock-to-Zone → Galv Stud Track & Frame → MEP Side-1 & Acoustic Wool → Side-2 Boarding & Q3 Skim Tape → Laser Flatness & Dust Clean → Hospital & Tower Fit-Outs

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: High-Rise Acoustic Double-Board Drywall TrainSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Gypsum Board & Mineral Wool → Forklift Board Stock-to-Zone (372 s) → Galv Stud Track & Frame (468 s) → MEP Side-1 & Acoustic Wool (642 s) → Side-2 Boarding & Q3 Skim Tape (444 s) → Laser Flatness & Dust Clean (312 s) → Hospital & Tower Fit-Outs.SUPPLIERGypsum Board &Mineral WoolI1.00 d1Forklift BoardStock-to-ZoneC/T 372 sI1.31 d2Galv Stud Track &FrameC/T 468 sI1.80 d3MEP Side-1 &Acoustic WoolC/T 642 sI0.91 d4Side-2 Boarding &Q3 Skim TapeC/T 444 sI0.51 d5Laser Flatness &Dust CleanC/T 312 sI0.60 dCUSTOMERHospital &Tower Fit-Outs45 / rooms

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Forklift Board Stock-to-Zone372 s10 min96%98.4%1845 (1.00 d)65
2. Galv Stud Track & Frame468 s12 min93%97.6%1459 (1.31 d)48
3. MEP Side-1 & Acoustic Wool642 s20 min85%93.8%1481 (1.80 d)29
4. Side-2 Boarding & Q3 Skim Tape444 s8 min95%97.4%941 (0.91 d)51
5. Laser Flatness & Dust Clean312 s5 min97%98.8%723 (0.51 d)77

Key figures

Takt time
600 s
Lead time
6.22 d
Value-added time
2,238 s
Process cycle efficiency (PCE)
1.3%
Rolled throughput yield (RTY)
86.7%
Customer demand per day
45 rooms
Line capacity per day
29 rooms
Bottleneck
MEP Side-1 & Acoustic Wool

Reading the bottleneck

The bottleneck is "MEP Side-1 & Acoustic Wool": it can process 29 rooms per day against a demand of 45 rooms, so it falls short of demand by 36.1%. Once downtime and scrap are counted, its cycle time grows from 642 s to 805 s, against a takt of 600 s. The largest loss at this step is equipment downtime (uptime 85%), about 113 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.