Bio-Pharma Cleanroom Stainless Exhaust Ducting

Product family: Zero-Leak Welded Plenum Install.

Flow: Prefab Orbital SS Duct Spools → Hanger Rod & Strut Grid → Spool Bolt-Up & Silicone Seal → HEPA Terminal Box Drop → SMACNA Pressure Decay Test → DOP Aerosol Filter Integrity → Pharma CapEx Contractors

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: Bio-Pharma Cleanroom Stainless Exhaust DuctingSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Prefab Orbital SS Duct Spools → Hanger Rod & Strut Grid (1,046 s) → Spool Bolt-Up & Silicone Seal (1,316 s) → HEPA Terminal Box Drop (1,806 s) → SMACNA Pressure Decay Test (1,249 s) → DOP Aerosol Filter Integrity (878 s) → Pharma CapEx Contractors.SUPPLIERPrefab OrbitalSS Duct SpoolsI1.00 d1Hanger Rod &Strut GridC/T 1,046 sI1.31 d2Spool Bolt-Up &Silicone SealC/T 1,316 sI1.81 d3HEPA Terminal BoxDropC/T 1,806 sI0.88 d4SMACNA PressureDecay TestC/T 1,249 sI0.50 d5DOP AerosolFilter IntegrityC/T 878 sI0.63 dCUSTOMERPharma CapExContractors16 / rooms

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Hanger Rod & Strut Grid1,046 s10 min96%98.4%616 (1.00 d)23
2. Spool Bolt-Up & Silicone Seal1,316 s12 min93%97.6%521 (1.31 d)17
3. HEPA Terminal Box Drop1,806 s20 min85%93.8%529 (1.81 d)10
4. SMACNA Pressure Decay Test1,249 s8 min95%97.4%314 (0.88 d)18
5. DOP Aerosol Filter Integrity878 s5 min97%98.8%28 (0.50 d)27

Key figures

Takt time
1,688 s
Lead time
6.36 d
Value-added time
6,295 s
Process cycle efficiency (PCE)
3.7%
Rolled throughput yield (RTY)
86.7%
Customer demand per day
16 rooms
Line capacity per day
10 rooms
Bottleneck
HEPA Terminal Box Drop

Reading the bottleneck

The bottleneck is "HEPA Terminal Box Drop": it can process 10 rooms per day against a demand of 16 rooms, so it falls short of demand by 36.1%. Once downtime and scrap are counted, its cycle time grows from 1,806 s to 2,265 s, against a takt of 1,688 s. The largest loss at this step is equipment downtime (uptime 85%), about 319 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.