500kW Commercial Flat-Roof Ballasted Solar Fit
Product family: Zero-Penetration Rooftop Array.
Flow: Tier-1 Bifacial PV & Racking → Roof Crane Material Lift & Layout → Protective EPDM Mat & Ballast → Module Clamp & DC Micro-Wire → Combiner, Inverter & AC Tie → IV Curve, Thermal Drone & Grid → Warehouse REIT Roofs
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. Roof Crane Material Lift & Layout | 930 s | 10 min | 96% | 98.4% | 7 | 18 (1.00 d) | 26 |
| 2. Protective EPDM Mat & Ballast | 1,170 s | 12 min | 93% | 97.6% | 5 | 23 (1.28 d) | 19 |
| 3. Module Clamp & DC Micro-Wire | 1,605 s | 20 min | 85% | 93.8% | 5 | 32 (1.78 d) | 11 |
| 4. Combiner, Inverter & AC Tie | 1,110 s | 8 min | 95% | 97.4% | 4 | 16 (0.89 d) | 21 |
| 5. IV Curve, Thermal Drone & Grid | 780 s | 5 min | 97% | 98.8% | 3 | 9 (0.50 d) | 31 |
Key figures
- Takt time
- 1,500 s
- Lead time
- 6.26 d
- Value-added time
- 5,595 s
- Process cycle efficiency (PCE)
- 3.3%
- Rolled throughput yield (RTY)
- 86.7%
- Customer demand per day
- 18 skids
- Line capacity per day
- 11 skids
- Bottleneck
- Module Clamp & DC Micro-Wire
Reading the bottleneck
The bottleneck is "Module Clamp & DC Micro-Wire": it can process 11 skids per day against a demand of 18 skids, so it falls short of demand by 37.4%. Once downtime and scrap are counted, its cycle time grows from 1,605 s to 2,013 s, against a takt of 1,500 s. The largest loss at this step is equipment downtime (uptime 85%), about 283 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Commercial Building MEP & Fit-Out Trades: Commercial Building MEP & Fit-Out Trades
- Grade-A Office Tower Floor MEP First-Fix Takt
- High-Rise Acoustic Double-Board Drywall Train
- Bio-Pharma Cleanroom Stainless Exhaust Ducting
- Warehouse ESFR High-Hazard Fire Sprinkler Grid
- Food & Pharma Seamless Polyurethane Screed Floor
- 10m/s Gearless High-Rise Elevator Shaft Install
- Smart Building BACnet / KNX HVAC Commissioning
- Industrial Refinery Turnaround Scaffold Build
- Multi-Tier Heavy Warehouse Steel Mezzanine
- Frameless Acoustic Office Glass Partitioning
- 70-Meter Internal Climbing Tower Crane Erection