Grade-A Office Tower Floor MEP First-Fix Takt

Product family: Weekly Floor Hand-Off Trains.

Flow: MEP Electrical & Duct Depots → Laser Slab Penetrations & Hang → Primary Duct & Chilled Loop → Busbar, Tray & Fire Sprinkler → Pressure & Continuity Check → Ceiling Close Sign-Off → Commercial Tower Developers

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: Grade-A Office Tower Floor MEP First-Fix TaktSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. MEP Electrical & Duct Depots → Laser Slab Penetrations & Hang (1,196 s) → Primary Duct & Chilled Loop (1,504 s) → Busbar, Tray & Fire Sprinkler (2,064 s) → Pressure & Continuity Check (1,427 s) → Ceiling Close Sign-Off (1,003 s) → Commercial Tower Developers.SUPPLIERMEP Electrical& Duct DepotsI1.00 d1Laser SlabPenetrations &…C/T 1,196 sI1.29 d2Primary Duct &Chilled LoopC/T 1,504 sI1.79 d3Busbar, Tray &Fire SprinklerC/T 2,064 sI0.93 d4Pressure &Continuity CheckC/T 1,427 sI0.50 d5Ceiling CloseSign-OffC/T 1,003 sI0.57 dCUSTOMERCommercialTower…14 / rooms

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Laser Slab Penetrations & Hang1,196 s10 min96%98.4%614 (1.00 d)20
2. Primary Duct & Chilled Loop1,504 s12 min93%97.6%418 (1.29 d)15
3. Busbar, Tray & Fire Sprinkler2,064 s20 min85%93.8%425 (1.79 d)9
4. Pressure & Continuity Check1,427 s8 min95%97.4%313 (0.93 d)16
5. Ceiling Close Sign-Off1,003 s5 min97%98.8%27 (0.50 d)24

Key figures

Takt time
1,929 s
Lead time
6.34 d
Value-added time
7,194 s
Process cycle efficiency (PCE)
4.2%
Rolled throughput yield (RTY)
86.7%
Customer demand per day
14 rooms
Line capacity per day
9 rooms
Bottleneck
Busbar, Tray & Fire Sprinkler

Reading the bottleneck

The bottleneck is "Busbar, Tray & Fire Sprinkler": it can process 9 rooms per day against a demand of 14 rooms, so it falls short of demand by 37.1%. Once downtime and scrap are counted, its cycle time grows from 2,064 s to 2,589 s, against a takt of 1,929 s. The largest loss at this step is equipment downtime (uptime 85%), about 364 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.