Grade-A Office Tower Floor MEP First-Fix Takt
Product family: Weekly Floor Hand-Off Trains.
Flow: MEP Electrical & Duct Depots → Laser Slab Penetrations & Hang → Primary Duct & Chilled Loop → Busbar, Tray & Fire Sprinkler → Pressure & Continuity Check → Ceiling Close Sign-Off → Commercial Tower Developers
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. Laser Slab Penetrations & Hang | 1,196 s | 10 min | 96% | 98.4% | 6 | 14 (1.00 d) | 20 |
| 2. Primary Duct & Chilled Loop | 1,504 s | 12 min | 93% | 97.6% | 4 | 18 (1.29 d) | 15 |
| 3. Busbar, Tray & Fire Sprinkler | 2,064 s | 20 min | 85% | 93.8% | 4 | 25 (1.79 d) | 9 |
| 4. Pressure & Continuity Check | 1,427 s | 8 min | 95% | 97.4% | 3 | 13 (0.93 d) | 16 |
| 5. Ceiling Close Sign-Off | 1,003 s | 5 min | 97% | 98.8% | 2 | 7 (0.50 d) | 24 |
Key figures
- Takt time
- 1,929 s
- Lead time
- 6.34 d
- Value-added time
- 7,194 s
- Process cycle efficiency (PCE)
- 4.2%
- Rolled throughput yield (RTY)
- 86.7%
- Customer demand per day
- 14 rooms
- Line capacity per day
- 9 rooms
- Bottleneck
- Busbar, Tray & Fire Sprinkler
Reading the bottleneck
The bottleneck is "Busbar, Tray & Fire Sprinkler": it can process 9 rooms per day against a demand of 14 rooms, so it falls short of demand by 37.1%. Once downtime and scrap are counted, its cycle time grows from 2,064 s to 2,589 s, against a takt of 1,929 s. The largest loss at this step is equipment downtime (uptime 85%), about 364 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Commercial Building MEP & Fit-Out Trades: Commercial Building MEP & Fit-Out Trades
- High-Rise Acoustic Double-Board Drywall Train
- Bio-Pharma Cleanroom Stainless Exhaust Ducting
- Warehouse ESFR High-Hazard Fire Sprinkler Grid
- Food & Pharma Seamless Polyurethane Screed Floor
- 10m/s Gearless High-Rise Elevator Shaft Install
- Smart Building BACnet / KNX HVAC Commissioning
- 500kW Commercial Flat-Roof Ballasted Solar Fit
- Industrial Refinery Turnaround Scaffold Build
- Multi-Tier Heavy Warehouse Steel Mezzanine
- Frameless Acoustic Office Glass Partitioning
- 70-Meter Internal Climbing Tower Crane Erection