5,000-Ton/Day Low-Carbon LC3 Cement Kiln Plant

Product family: Calcined Clay Blended Cement.

Flow: Limestone & Kaolin Clay Pit → Raw Meal Vertical Roller Mill → 5-Stage Preheater & Kiln 1450°C → Clinker Grate Cooler & RDF → Finish Ball/VRM Cement Grind → Pneumatic Silo & 25kg Bag → Ready-Mix & Precast Silos

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: 5,000-Ton/Day Low-Carbon LC3 Cement Kiln PlantSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Limestone & Kaolin Clay Pit → Raw Meal Vertical Roller Mill (10.8 s) → 5-Stage Preheater & Kiln 1450°C (18.1 s) → Clinker Grate Cooler & RDF (13.5 s) → Finish Ball/VRM Cement Grind (11.5 s) → Pneumatic Silo & 25kg Bag (8.8 s) → Ready-Mix & Precast Silos.SUPPLIERLimestone &Kaolin Clay PitI1.40 d1Raw Meal VerticalRoller MillC/T 10.8 sI1.80 d25-Stage Preheater& Kiln 1450°CC/T 18.1 sI1.20 d3Clinker GrateCooler & RDFC/T 13.5 sI0.70 d4Finish Ball/VRMCement GrindC/T 11.5 sI0.80 d5Pneumatic Silo &25kg BagC/T 8.8 sI1.20 dCUSTOMERReady-Mix &Precast Silos4,800 / tonnes

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Raw Meal Vertical Roller Mill10.8 s20 min95%99.1%5,7606,720 (1.40 d)6,974
2. 5-Stage Preheater & Kiln 1450°C18.1 s45 min84%96.4%7,2008,640 (1.80 d)3,543
3. Clinker Grate Cooler & RDF13.5 s15 min93%98.4%3,8405,760 (1.20 d)5,414
4. Finish Ball/VRM Cement Grind11.5 s5 min96%98.8%1,4403,360 (0.70 d)6,598
5. Pneumatic Silo & 25kg Bag8.8 s8 min97%99.5%1,2003,840 (0.80 d)8,673

Key figures

Takt time
16.9 s
Lead time
7.10 d
Value-added time
62.7 s
Process cycle efficiency (PCE)
0.011%
Rolled throughput yield (RTY)
92.4%
Customer demand per day
4,800 tonnes
Line capacity per day
3,543 tonnes
Bottleneck
5-Stage Preheater & Kiln 1450°C

Reading the bottleneck

The bottleneck is "5-Stage Preheater & Kiln 1450°C": it can process 3,543 tonnes per day against a demand of 4,800 tonnes, so it falls short of demand by 26.2%. Once downtime and scrap are counted, its cycle time grows from 18.1 s to 22.4 s, against a takt of 16.9 s. The largest loss at this step is equipment downtime (uptime 84%), about 3.4 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.