Autoclaved Aerated Concrete (AAC) Thermal Block

Product family: Precision Thin-Bed Blocks.

Flow: Silica Sand, Lime & Al Paste → Sand Wet Ball Mill & Mixer → Pre-Rise Expansion Mold Hold → Wire-Harp Precision Cake Cut → 190°C Steam Autoclave Cure → De-Hack & Hood Shrink Pallet → Residential Masonry

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: Autoclaved Aerated Concrete (AAC) Thermal BlockSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Silica Sand, Lime & Al Paste → Sand Wet Ball Mill & Mixer (123 s) → Pre-Rise Expansion Mold Hold (206 s) → Wire-Harp Precision Cake Cut (154 s) → 190°C Steam Autoclave Cure (131 s) → De-Hack & Hood Shrink Pallet (100 s) → Residential Masonry.SUPPLIERSilica Sand,Lime & Al PasteI1.40 d1Sand Wet BallMill & MixerC/T 123 sI1.80 d2Pre-RiseExpansion Mold…C/T 206 sI1.20 d3Wire-HarpPrecision Cake…C/T 154 sI0.70 d4190°C SteamAutoclave CureC/T 131 sI0.80 d5De-Hack & HoodShrink PalletC/T 100 sI1.20 dCUSTOMERResidentialMasonry420 / tonnes

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Sand Wet Ball Mill & Mixer123 s20 min95%99.1%504588 (1.40 d)612
2. Pre-Rise Expansion Mold Hold206 s45 min84%96.4%630756 (1.80 d)311
3. Wire-Harp Precision Cake Cut154 s15 min93%98.4%336504 (1.20 d)475
4. 190°C Steam Autoclave Cure131 s5 min96%98.8%126294 (0.70 d)579
5. De-Hack & Hood Shrink Pallet100 s8 min97%99.5%105336 (0.80 d)763

Key figures

Takt time
193 s
Lead time
7.11 d
Value-added time
714 s
Process cycle efficiency (PCE)
0.12%
Rolled throughput yield (RTY)
92.4%
Customer demand per day
420 tonnes
Line capacity per day
311 tonnes
Bottleneck
Pre-Rise Expansion Mold Hold

Reading the bottleneck

The bottleneck is "Pre-Rise Expansion Mold Hold": it can process 311 tonnes per day against a demand of 420 tonnes, so it falls short of demand by 25.9%. Once downtime and scrap are counted, its cycle time grows from 206 s to 254 s, against a takt of 193 s. The largest loss at this step is equipment downtime (uptime 84%), about 39.2 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.