Pultruded Glass-Fiber Composite Corrosion Rebar

Product family: Salt-Proof Bridge Deck Rebar.

Flow: Glass Fiber Roving → 48-Creel Glass Fiber Guide → Vinyl Ester Heated Resin Bath → Heated Pultrusion Cure Die → Helical Sand-Coat Bond Wrap → Saw Cut-to-Length & Tensile QC → Marine & Bridge Concrete

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: Pultruded Glass-Fiber Composite Corrosion RebarSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Glass Fiber Roving → 48-Creel Glass Fiber Guide (28.8 s) → Vinyl Ester Heated Resin Bath (48.0 s) → Heated Pultrusion Cure Die (36.0 s) → Helical Sand-Coat Bond Wrap (30.6 s) → Saw Cut-to-Length & Tensile QC (23.4 s) → Marine & Bridge Concrete.SUPPLIERGlass FiberRovingI1.40 d148-Creel GlassFiber GuideC/T 28.8 sI1.80 d2Vinyl EsterHeated Resin BathC/T 48.0 sI1.20 d3Heated PultrusionCure DieC/T 36.0 sI0.70 d4Helical Sand-CoatBond WrapC/T 30.6 sI0.80 d5Saw Cut-to-Length& Tensile QCC/T 23.4 sI1.20 dCUSTOMERMarine & BridgeConcrete1,800 / parts

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. 48-Creel Glass Fiber Guide28.8 s20 min95%99.1%2,1602,520 (1.40 d)2,615
2. Vinyl Ester Heated Resin Bath48.0 s45 min84%96.4%2,7003,240 (1.80 d)1,336
3. Heated Pultrusion Cure Die36.0 s15 min93%98.4%1,4402,160 (1.20 d)2,030
4. Helical Sand-Coat Bond Wrap30.6 s5 min96%98.8%5401,260 (0.70 d)2,480
5. Saw Cut-to-Length & Tensile QC23.4 s8 min97%99.5%4501,440 (0.80 d)3,262

Key figures

Takt time
45.0 s
Lead time
7.10 d
Value-added time
167 s
Process cycle efficiency (PCE)
0.029%
Rolled throughput yield (RTY)
92.4%
Customer demand per day
1,800 parts
Line capacity per day
1,336 parts
Bottleneck
Vinyl Ester Heated Resin Bath

Reading the bottleneck

The bottleneck is "Vinyl Ester Heated Resin Bath": it can process 1,336 parts per day against a demand of 1,800 parts, so it falls short of demand by 25.8%. Once downtime and scrap are counted, its cycle time grows from 48.0 s to 59.3 s, against a takt of 45.0 s. The largest loss at this step is equipment downtime (uptime 84%), about 9.1 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.

Other scenarios in this family

More scenarios of Cement, Concrete, Bricks & Materials: Cement, Concrete, Bricks & Materials