100m/min Fire & Moisture Gypsum Plasterboard

Product family: 12.5mm Paper-Lined Drywall.

Flow: FGD Desulfurization Gypsum → Rotary Kettle Stucco Calciner → Pin Mixer & Slurry Form Table → 400m Setting Belt & Knife Cut → Multi-Deck Hot Gas Zone Dryer → End Tape Bundle & Batten Pal → Building Material Merchants

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: 100m/min Fire & Moisture Gypsum PlasterboardSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. FGD Desulfurization Gypsum → Rotary Kettle Stucco Calciner (1.6 s) → Pin Mixer & Slurry Form Table (2.7 s) → 400m Setting Belt & Knife Cut (2.0 s) → Multi-Deck Hot Gas Zone Dryer (1.7 s) → End Tape Bundle & Batten Pal (1.3 s) → Building Material Merchants.SUPPLIERFGDDesulfurizationGypsumI1.40 d1Rotary KettleStucco CalcinerC/T 1.6 sI1.80 d2Pin Mixer &Slurry Form TableC/T 2.7 sI1.20 d3400m Setting Belt& Knife CutC/T 2.0 sI0.70 d4Multi-Deck HotGas Zone DryerC/T 1.7 sI0.80 d5End Tape Bundle &Batten PalC/T 1.3 sI1.20 dCUSTOMERBuildingMaterial…32,000 / parts

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Rotary Kettle Stucco Calciner1.6 s20 min95%99.1%38,40044,800 (1.40 d)47,072
2. Pin Mixer & Slurry Form Table2.7 s45 min84%96.4%48,00057,600 (1.80 d)23,753
3. 400m Setting Belt & Knife Cut2.0 s15 min93%98.4%25,60038,400 (1.20 d)36,548
4. Multi-Deck Hot Gas Zone Dryer1.7 s5 min96%98.8%9,60022,400 (0.70 d)44,634
5. End Tape Bundle & Batten Pal1.3 s8 min97%99.5%8,00025,600 (0.80 d)58,711

Key figures

Takt time
2.5 s
Lead time
7.10 d
Value-added time
9.3 s
Process cycle efficiency (PCE)
0.002%
Rolled throughput yield (RTY)
92.4%
Customer demand per day
32,000 parts
Line capacity per day
23,753 parts
Bottleneck
Pin Mixer & Slurry Form Table

Reading the bottleneck

The bottleneck is "Pin Mixer & Slurry Form Table": it can process 23,753 parts per day against a demand of 32,000 parts, so it falls short of demand by 25.8%. Once downtime and scrap are counted, its cycle time grows from 2.7 s to 3.3 s, against a takt of 2.5 s. The largest loss at this step is equipment downtime (uptime 84%), about 0.5 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.