120m³/Hr Automated Ready-Mix Concrete Batch

Product family: Low-Carbon Transit Mix.

Flow: Washed Sand, Gravel & Cement → Order Dispatch & Moisture Probe → Twin-Shaft Wet Mixer Blend → Slump Torque & Water Trim → 8m³ Drum Transit GPS Route → Site Chute Pour & Washback → City Pouring Job Sites

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: 120m³/Hr Automated Ready-Mix Concrete BatchSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Washed Sand, Gravel & Cement → Order Dispatch & Moisture Probe (216 s) → Twin-Shaft Wet Mixer Blend (361 s) → Slump Torque & Water Trim (270 s) → 8m³ Drum Transit GPS Route (230 s) → Site Chute Pour & Washback (176 s) → City Pouring Job Sites.SUPPLIERWashed Sand,Gravel & CementI1.40 d1Order Dispatch &Moisture ProbeC/T 216 sI1.80 d2Twin-Shaft WetMixer BlendC/T 361 sI1.20 d3Slump Torque &Water TrimC/T 270 sI0.70 d48m³ Drum TransitGPS RouteC/T 230 sI0.80 d5Site Chute Pour &WashbackC/T 176 sI1.20 dCUSTOMERCity PouringJob Sites160 / batches

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Order Dispatch & Moisture Probe216 s20 min95%99.1%192224 (1.40 d)231
2. Twin-Shaft Wet Mixer Blend361 s45 min84%96.4%240288 (1.80 d)117
3. Slump Torque & Water Trim270 s15 min93%98.4%128192 (1.20 d)179
4. 8m³ Drum Transit GPS Route230 s5 min96%98.8%48112 (0.70 d)219
5. Site Chute Pour & Washback176 s8 min97%99.5%40128 (0.80 d)286

Key figures

Takt time
338 s
Lead time
7.12 d
Value-added time
1,253 s
Process cycle efficiency (PCE)
0.33%
Rolled throughput yield (RTY)
92.4%
Customer demand per day
160 batches
Line capacity per day
117 batches
Bottleneck
Twin-Shaft Wet Mixer Blend

Reading the bottleneck

The bottleneck is "Twin-Shaft Wet Mixer Blend": it can process 117 batches per day against a demand of 160 batches, so it falls short of demand by 26.8%. Once downtime and scrap are counted, its cycle time grows from 361 s to 446 s, against a takt of 338 s. The largest loss at this step is equipment downtime (uptime 84%), about 68.8 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.

Other scenarios in this family

More scenarios of Cement, Concrete, Bricks & Materials: Cement, Concrete, Bricks & Materials