1050°C Tunnel Kiln Hollow Thermal Clay Brick

Product family: Rectified Ground Thermal Bricks.

Flow: Quarry Red Clay & Sawdust → Clay Crusher & Vacuum Extrude → Precision Wire Multi-Cutter → 48h Waste-Heat Tunnel Dryer → 1050°C Gas Firing & Cool Kiln → Diamond Grind & Shrink Stack → Residential Builders

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: 1050°C Tunnel Kiln Hollow Thermal Clay BrickSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Quarry Red Clay & Sawdust → Clay Crusher & Vacuum Extrude (81.0 s) → Precision Wire Multi-Cutter (135 s) → 48h Waste-Heat Tunnel Dryer (101 s) → 1050°C Gas Firing & Cool Kiln (86.0 s) → Diamond Grind & Shrink Stack (66.0 s) → Residential Builders.SUPPLIERQuarry Red Clay& SawdustI1.40 d1Clay Crusher &Vacuum ExtrudeC/T 81.0 sI1.80 d2Precision WireMulti-CutterC/T 135 sI1.20 d348h Waste-HeatTunnel DryerC/T 101 sI0.70 d41050°C Gas Firing& Cool KilnC/T 86.0 sI0.80 d5Diamond Grind &Shrink StackC/T 66.0 sI1.20 dCUSTOMERResidentialBuilders640 / tonnes

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Clay Crusher & Vacuum Extrude81.0 s20 min95%99.1%768896 (1.40 d)930
2. Precision Wire Multi-Cutter135 s45 min84%96.4%9601,152 (1.80 d)475
3. 48h Waste-Heat Tunnel Dryer101 s15 min93%98.4%512768 (1.20 d)724
4. 1050°C Gas Firing & Cool Kiln86.0 s5 min96%98.8%192448 (0.70 d)882
5. Diamond Grind & Shrink Stack66.0 s8 min97%99.5%160512 (0.80 d)1,156

Key figures

Takt time
127 s
Lead time
7.11 d
Value-added time
469 s
Process cycle efficiency (PCE)
0.081%
Rolled throughput yield (RTY)
92.4%
Customer demand per day
640 tonnes
Line capacity per day
475 tonnes
Bottleneck
Precision Wire Multi-Cutter

Reading the bottleneck

The bottleneck is "Precision Wire Multi-Cutter": it can process 475 tonnes per day against a demand of 640 tonnes, so it falls short of demand by 25.8%. Once downtime and scrap are counted, its cycle time grows from 135 s to 167 s, against a takt of 127 s. The largest loss at this step is equipment downtime (uptime 84%), about 25.7 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.