Closed-Loop Manufactured Concrete Sand Wash

Product family: Zero-Silt Quarry Aggregates.

Flow: Quarry Crushed Fines <4mm → Hydrocyclone Silt Washing → Double-Deck Dewatering Screen → Thickener Tank & Filter Press → Cake Clay Reclamation Dump → 92%-Recycled Water Conveyor → Ready-Mix Concrete Plants

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: Closed-Loop Manufactured Concrete Sand WashSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Quarry Crushed Fines <4mm → Hydrocyclone Silt Washing (41.0 s) → Double-Deck Dewatering Screen (68.0 s) → Thickener Tank & Filter Press (51.0 s) → Cake Clay Reclamation Dump (43.0 s) → 92%-Recycled Water Conveyor (33.0 s) → Ready-Mix Concrete Plants.SUPPLIERQuarry CrushedFines <4mmI1.40 d1Hydrocyclone SiltWashingC/T 41.0 sI1.80 d2Double-DeckDewatering ScreenC/T 68.0 sI1.20 d3Thickener Tank &Filter PressC/T 51.0 sI0.70 d4Cake ClayReclamation DumpC/T 43.0 sI0.80 d592%-RecycledWater ConveyorC/T 33.0 sI1.20 dCUSTOMERReady-MixConcrete Plants850 / tonnes

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Hydrocyclone Silt Washing41.0 s20 min95%99.1%1,0201,190 (1.40 d)1,217
2. Double-Deck Dewatering Screen68.0 s45 min84%96.4%1,2751,530 (1.80 d)622
3. Thickener Tank & Filter Press51.0 s15 min93%98.4%6801,020 (1.20 d)949
4. Cake Clay Reclamation Dump43.0 s5 min96%98.8%255595 (0.70 d)1,169
5. 92%-Recycled Water Conveyor33.0 s8 min97%99.5%213680 (0.80 d)1,523

Key figures

Takt time
63.5 s
Lead time
7.10 d
Value-added time
236 s
Process cycle efficiency (PCE)
0.062%
Rolled throughput yield (RTY)
92.4%
Customer demand per day
850 tonnes
Line capacity per day
622 tonnes
Bottleneck
Double-Deck Dewatering Screen

Reading the bottleneck

The bottleneck is "Double-Deck Dewatering Screen": it can process 622 tonnes per day against a demand of 850 tonnes, so it falls short of demand by 26.9%. Once downtime and scrap are counted, its cycle time grows from 68.0 s to 84.0 s, against a takt of 63.5 s. The largest loss at this step is equipment downtime (uptime 84%), about 13.0 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.

Other scenarios in this family

More scenarios of Cement, Concrete, Bricks & Materials: Cement, Concrete, Bricks & Materials