Tile Adhesive & External Facade Dry-Mortar Tower

Product family: 25kg Polymer-Modified Bags.

Flow: Dried Quartz Sand & Cellulose → Fluid-Bed Sand Dry & Sieve → Automated Micro-Additive Dose → High-Speed Ploughshare Mix → 8-Spout Turbine Bag Packer → Robot Bag Stack & Weather Wrap → Tilers & Facade Crews

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: Tile Adhesive & External Facade Dry-Mortar TowerSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Dried Quartz Sand & Cellulose → Fluid-Bed Sand Dry & Sieve (91.0 s) → Automated Micro-Additive Dose (152 s) → High-Speed Ploughshare Mix (114 s) → 8-Spout Turbine Bag Packer (97.0 s) → Robot Bag Stack & Weather Wrap (74.0 s) → Tilers & Facade Crews.SUPPLIERDried QuartzSand &CelluloseI1.40 d1Fluid-Bed SandDry & SieveC/T 91.0 sI1.80 d2AutomatedMicro-Additive…C/T 152 sI1.20 d3High-SpeedPloughshare MixC/T 114 sI0.70 d48-Spout TurbineBag PackerC/T 97.0 sI0.80 d5Robot Bag Stack &Weather WrapC/T 74.0 sI1.20 dCUSTOMERTilers & FacadeCrews380 / tonnes

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Fluid-Bed Sand Dry & Sieve91.0 s20 min95%99.1%456532 (1.40 d)548
2. Automated Micro-Additive Dose152 s45 min84%96.4%570684 (1.80 d)278
3. High-Speed Ploughshare Mix114 s15 min93%98.4%304456 (1.20 d)424
4. 8-Spout Turbine Bag Packer97.0 s5 min96%98.8%114266 (0.70 d)518
5. Robot Bag Stack & Weather Wrap74.0 s8 min97%99.5%95304 (0.80 d)679

Key figures

Takt time
142 s
Lead time
7.11 d
Value-added time
528 s
Process cycle efficiency (PCE)
0.14%
Rolled throughput yield (RTY)
92.4%
Customer demand per day
380 tonnes
Line capacity per day
278 tonnes
Bottleneck
Automated Micro-Additive Dose

Reading the bottleneck

The bottleneck is "Automated Micro-Additive Dose": it can process 278 tonnes per day against a demand of 380 tonnes, so it falls short of demand by 26.8%. Once downtime and scrap are counted, its cycle time grows from 152 s to 188 s, against a takt of 142 s. The largest loss at this step is equipment downtime (uptime 84%), about 29.0 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.