Automotive ASIL-D EV BMS Mainboard SMT
Product family: High-Voltage Sense Boards.
Flow: Automotive-Grade PCB Supplier → Vacuum Stencil & 3D SPI → Auto Dual-Gantry SMD → Nitrogen Reflow & AXI X-Ray → Press-Fit Iso-Conn & Gel Coat → HV Isolation Boundary Test → EV Battery Integrators
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. Vacuum Stencil & 3D SPI | 18.9 s | 25 min | 95% | 98.6% | 1,280 | 1,920 (1.20 d) | 2,583 |
| 2. Auto Dual-Gantry SMD | 27.7 s | 35 min | 91% | 97.4% | 1,280 | 2,240 (1.40 d) | 1,644 |
| 3. Nitrogen Reflow & AXI X-Ray | 36.1 s | 45 min | 84% | 95.4% | 1,600 | 2,880 (1.80 d) | 1,139 |
| 4. Press-Fit Iso-Conn & Gel Coat | 26.3 s | 18 min | 93% | 98.1% | 640 | 1,600 (1.00 d) | 1,780 |
| 5. HV Isolation Boundary Test | 23.0 s | 15 min | 95% | 98.8% | 400 | 1,280 (0.80 d) | 2,057 |
Key figures
- Takt time
- 33.8 s
- Lead time
- 7.40 d
- Value-added time
- 132 s
- Process cycle efficiency (PCE)
- 0.033%
- Rolled throughput yield (RTY)
- 88.8%
- Customer demand per day
- 1,600 boards
- Line capacity per day
- 1,139 boards
- Bottleneck
- Nitrogen Reflow & AXI X-Ray
Reading the bottleneck
The bottleneck is "Nitrogen Reflow & AXI X-Ray": it can process 1,139 boards per day against a demand of 1,600 boards, so it falls short of demand by 28.8%. Once downtime and scrap are counted, its cycle time grows from 36.1 s to 45.0 s, against a takt of 33.8 s. The largest loss at this step is equipment downtime (uptime 84%), about 6.9 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of PCB SMT & Box-Build EMS: PCB SMT & Box-Build EMS
- PCB SMT Pick-and-Place & Box Build
- 64T64R 5G Massive-MIMO Antenna PCB Line
- 77GHz Automotive ADAS Radar Sensor PCB
- ISO-13485 Medical Ultrasound Beamformer PCB
- Dual-Socket AI GPU Server Motherboard
- NB-IoT Ultrasonic Smart Water/Gas Meter
- Three-Phase Industrial VFD Inverter Gate Board
- Modular DIN-Rail Industrial Safety PLC I/O
- PCI-PTS Secure EMV Payment Terminal PCBA
- Matter & Thread Smart Home Gateway Line
- Rigid-Flex Polyimide Satellite Bus Board